p2/data/questions-en.js
2026-06-15 22:42:09 +02:00

2166 lines
No EOL
148 KiB
JavaScript
Raw Blame History

This file contains ambiguous Unicode characters

This file contains Unicode characters that might be confused with other characters. If you think that this is intentional, you can safely ignore this warning. Use the Escape button to reveal them.

window.QUESTIONS_EN = [
{
exam: 1,
qnum: 1,
q: "Which statement describes the project context?",
opts: [
"It should be understood by stakeholders so that the principles are applied appropriately",
"It explains how each aspect of project management should be applied for the processes to be effective",
"It guides the progression from pre-project activity through the stages of the project lifecycle",
"It ensures an understanding of the needs of stakeholders, and the relationships between them"
],
correct: 0,
explanation: [
"A. Correct. The project context is one of the five integrated elements of PRINCE2. It influences how the principles, practices, and processes are applied by the people involved to ensure that the method is appropriate to the project context. See 1.2",
"B. Incorrect. The PRINCE2 practices describe aspects of project management that must be addressed continually as the project moves through its lifecycle, and explain the specific treatment required for that aspect of project management for the PRINCE2 processes to be effective and why they are necessary. See 1.2, 4.1",
"C. Incorrect. The seven processes describe the entire project lifecycle, from pre-project activity to project closure. Each process has a checklist of recommended activities, products, and associated responsibilities. See 1.2, 13.1",
"D. Incorrect. The people element enables individuals to work together effectively on a project. Without people, projects cannot function; the ability to build a project team and manage relationships with stakeholders is essential for project success. See 3.1"
]
},
{
exam: 1,
qnum: 2,
q: "Which is a characteristic of a project that distinguishes it from business as usual?",
opts: [
"Projects continue after business as usual resumes",
"Projects include ongoing management of operations",
"Every project is different from previous projects",
"Project work is generally less risky than business as usual"
],
correct: 2,
explanation: [
"A. Incorrect. A project is a temporary organization. It has a defined start and end, so it does not continue after normal operations resume. See 1.1",
"B. Incorrect. Business as usual is the day-to-day management of operations in an organization, whereas a project is a temporary structure set up to introduce a change. See 1.1",
"C. Correct. Being unique is a characteristic of a project. Because every project is different from previous projects, it introduces a degree of uncertainty and risk. See 1.1",
"D. Incorrect. Because every project is unique, project work is generally riskier than business as usual operations. See 1.1"
]
},
{
exam: 1,
qnum: 3,
q: "The project board has decided that the project must be closed prematurely because the external environment has changed. Which principle is being applied?",
opts: [
"Learn from experience",
"Tailor to suit the project",
"Manage by exception",
"Ensure continued business justification"
],
correct: 3,
explanation: [
"A. Incorrect. The 'learn from experience' principle states that PRINCE2 project teams should learn from previous projects and continue to capture lessons throughout the project lifecycle. See 2.2",
"B. Incorrect. The 'tailor to suit the project' principle ensures that PRINCE2 is adapted to the context, scale, complexity, geography, and risk of the project. See 2.6",
"C. Incorrect. The 'manage by exception' principle involves setting tolerances for performance targets to delegate authority for decision-making. See 2.4",
"D. Correct. The 'ensure continued business justification' principle requires that a project has a justification that remains valid throughout its lifecycle. If the justification disappears (e.g., due to changes in the external environment), the project should be stopped or changed. See 2.1"
]
},
{
exam: 1,
qnum: 4,
q: "Which statement about the 'define roles, responsibilities, and relationships' principle is CORRECT?",
opts: [
"The project management team should consist exclusively of internal stakeholders",
"An organization's day-to-day management structures are likely to be suited to control the project work",
"The project board should exclude external supplier representatives",
"Suppliers are stakeholders that can be external to the business"
],
correct: 3,
explanation: [
"A. Incorrect. A project often involves a cross-functional team of people with different interests, potentially including external suppliers or partners. It does not have to consist exclusively of internal stakeholders. See 2.3",
"B. Incorrect. Projects are temporary organizations and require structures that differ from an organization's day-to-day, line-based management structures to manage cross-functionality and temporariness. See 2.3",
"C. Incorrect. The project board must represent the three primary stakeholders: business, user, and supplier. External suppliers are therefore not excluded if they play a primary role. See 2.3",
"D. Correct. Suppliers provide the resources and expertise required to realize the project products. They can be either internal (another department) or external to the business. See 2.3"
]
},
{
exam: 1,
qnum: 5,
q: "Which principle is applied when setting boundaries for the seven aspects of performance to enable the project manager to work effectively?",
opts: [
"Manage by exception",
"Learn from experience",
"Tailor to suit the project",
"Define roles, responsibilities, and relationships"
],
correct: 0,
explanation: [
"A. Correct. The 'manage by exception' principle defines tolerances (boundaries) for the project performance indicators (cost, time, quality, scope, benefits, risk, and sustainability) to enable efficient delegation. See 2.4",
"B. Incorrect. The 'learn from experience' principle focuses on using lessons from the past to prevent mistakes and improve performance. See 2.2",
"C. Incorrect. The 'tailor to suit the project' principle ensures that the method fits the specific characteristics and environment of the project. See 2.6",
"D. Incorrect. The 'define roles, responsibilities, and relationships' principle focuses on setting up the temporary project organization structure. See 2.3"
]
},
{
exam: 1,
qnum: 6,
q: "What does the 'ensure continued business justification' principle facilitate?",
opts: [
"That the project has a business stakeholder to ensure the investment continues to be justified",
"That the project remains desirable, viable and achievable as the project progresses",
"That products delivered by the project meet their quality requirements",
"That the PRINCE2 project management method is suited to the scale of investment"
],
correct: 1,
explanation: [
"A. Incorrect. While the business role is represented (by the executive), the purpose of the principle itself is broader: to ensure that the investment remains justified in terms of desirability, viability, and achievability. See 2.1",
"B. Correct. This principle ensures that there is a documented justification for starting and continuing the investment, and that the project remains consistently desirable, viable, and achievable throughout its duration. See 2.1",
"C. Incorrect. This is more closely linked to the 'focus on products' principle and the 'quality' practice, which ensure that products meet specified criteria. See 2.5, 8.1",
"D. Incorrect. This relates to the 'tailor to suit the project' principle, where the method is adapted to the scale and context of the project. See 2.6"
]
},
{
exam: 1,
qnum: 7,
q: "Which statement describes how the principles support effective project management?",
opts: [
"They allow the project team to decide how the method should be applied on the project",
"They take into account industry-specific models as PRINCE2 is generic",
"They rely on a common vocabulary that must be applied as defined in PRINCE2",
"They must be applied in the same way to all projects within an organization"
],
correct: 0,
explanation: [
"A. Correct. The seven principles form the foundation of PRINCE2. They are universally applicable and enable the project team to reflect and decide how the method can best be applied and tailored for the specific context of the project. See 2.0",
"B. Incorrect. Although PRINCE2 is generic and can be used in any industry, this is not the core definition of how the principles support effective management. The principles themselves are not industry-specific. See 2.0",
"C. Incorrect. While a common language is a benefit of PRINCE2, this is a characteristic of the method as a whole, not the specific way the universal principles guide good project management. See 1.1",
"D. Incorrect. The principles are universally applicable, but how they are shaped in practice depends on the project via the 'tailor to suit the project' principle. They are not blindly applied in exactly the same way. See 2.6"
]
},
{
exam: 1,
qnum: 8,
q: "Which statement describes leadership on a project?",
opts: [
"It is best done through collaboration across the project ecosystem",
"It is the set of shared attitudes, values and goals for the project",
"It is a control that takes place when a specific event occurs",
"It is instructing the execution of tasks in line with agreed ways of working"
],
correct: 0,
explanation: [
"A. Correct. Leadership within PRINCE2 7 is viewed as a collaborative and co-creative effort. Effective leadership stimulates collaboration across organizational boundaries and involves the entire project ecosystem. See 3.1",
"B. Incorrect. This describes the project culture ('the set of shared attitudes, values, and goals') rather than leadership itself, though leadership influences culture. See 3.1.1",
"C. Incorrect. This is the definition of an event-driven control within progress management, not of leadership. See 12.2.1",
"D. Incorrect. This is the definition of management or purely directive guidance ('instructing the execution of tasks'), which differs from the motivating and direction-setting nature of modern leadership. See 3.3"
]
},
{
exam: 1,
qnum: 9,
q: "Which is a definition of co-creation?",
opts: [
"Working with key influencers to ensure the agreed ways of working are adopted by all areas of the project ecosystem",
"Modifying any of the approved management products that are part of the project baseline",
"Ensuring decisions made at stage boundaries are informed by continued business justification",
"Applying management control whenever a specific event takes place"
],
correct: 0,
explanation: [
"A. Correct. Co-creation within the people element is the active collaboration with stakeholders and influencers across the project ecosystem to ensure ways of working are jointly designed, accepted, and supported. See 3.1",
"B. Incorrect. This describes implementing a change to a baselined product (change control), which is an activity within the 'issues' practice. See 11.1",
"C. Incorrect. This describes a control mechanism linked to the 'ensure continued business justification' and 'manage by stages' principles, not co-creation. See 2.1, 2.7",
"D. Incorrect. This is the definition of an event-driven control, belonging to the 'progress' practice. See 12.2.1"
]
},
{
exam: 1,
qnum: 10,
q: "Which is NOT an aspect of leadership?",
opts: [
"Instructing the execution of tasks in line with agreed ways of working",
"Motivating people to achieve the objectives of a project",
"Persuading, influencing, and co-creating with stakeholders",
"Regularly asking for feedback to remain aligned with the project objectives"
],
correct: 0,
explanation: [
"A. Correct (as being NOT an aspect of leadership). Merely transactionally or directively instructing on tasks belongs to traditional management duties and is not the distinguishing feature of motivating leadership. See 3.3",
"B. Incorrect. Motivating people to achieve shared goals is a core aspect of effective project leadership. See 3.3",
"C. Incorrect. Persuading, influencing, and encouraging co-creation with stakeholders are essential relational skills of a project leader. See 3.3",
"D. Incorrect. An open attitude that actively seeks feedback to maintain focus and alignment is an important characteristic of modern leadership. See 3.3"
]
},
{
exam: 1,
qnum: 11,
q: "Which activity should be managed carefully as part of 'leading across organizational boundaries', because it is likely to be performed by people outside the project team?",
opts: [
"Securing funding from the business layer for the business case",
"Integrating new products into each impacted area of the business",
"Gaining commitment for the realization of benefits post-project",
"Delivering the products in line with agreed quality specifications"
],
correct: 1,
explanation: [
"A. Incorrect. Although funding comes from the business layer, approving the business case is a direct responsibility within governance (board/executive) and falls within formal project boundaries. See 5.1",
"B. Correct. Actually integrating project results into operational lines (business as usual) is done by operational managers and staff outside the direct project team. This requires leadership across organizational boundaries to embed the change. See 3.2",
"C. Incorrect. Committing to and monitoring post-project benefits is primarily assigned to the senior user and line organization, but product integration and adoption is the direct operational boundary activity during transition. See 3.2, 5.3.3",
"D. Incorrect. Delivering products according to specifications is the core responsibility of the project team itself (via team managers and specialists) and does not cross these operational organizational boundaries in the same way. See 5.3.5"
]
},
{
exam: 1,
qnum: 12,
q: "Why is change management important in a project?",
opts: [
"Because stakeholders must understand which organizational areas are impacted by the project",
"Because the project products must be described and subjected to change control",
"Because confidence is needed that the project can meet its scope objectives and continues to be justified",
"Because user's quality expectations of the project products should be understood"
],
correct: 0,
explanation: [
"A. Correct. Change management focuses on the human and organizational side of change. It helps stakeholders see how the project impacts their work processes, culture, and structure, which is crucial for adoption. See 3.4",
"B. Incorrect. This describes configuration management or product change control (issue and change management), which relates to the products themselves and not organizational change management. See 11.1",
"C. Incorrect. This is linked to overall project control and monitoring the business case (business justification), which is broader than the specific focus of change management. See 5.1",
"D. Incorrect. Understanding quality expectations is a task within the 'quality' practice and starts with defining the project product description, not specifically with change management. See 8.1"
]
},
{
exam: 1,
qnum: 13,
q: "Which statement about capability and competence within a project is CORRECT?",
opts: [
"Teams should consist of members with similar capabilities and competencies",
"Team members are likely to perform differently depending on the structure of the team",
"Standard roles and responsibilities should be used, focused on the project's needs",
"Career progression of project team members is often the responsibility of the project manager"
],
correct: 1,
explanation: [
"A. Incorrect. Effective project teams require a mix of complementary (different) skills, roles, and competencies to address both technical and organizational aspects. See 3.3",
"B. Correct. Individual performance is heavily influenced by team dynamics, culture, and how the team is structured and led. The context and setup of the team partly determine its members' success. See 3.3",
"C. Incorrect. Although PRINCE2 provides role definitions, roles must always be explicitly tailored and adapted to the specific needs, scale, and context of the project, rather than using rigid standards. See 2.6, 5.1",
"D. Incorrect. Long-term career development is the responsibility of the line organization or the employee themselves, not the temporary project manager. See 3.3"
]
},
{
exam: 1,
qnum: 14,
q: "What is a description of a purpose of the change management approach?",
opts: [
"To describe how proposals to change the project baseline should be recorded and approved",
"To describe the standards required to deliver products that meet user's expectations",
"To define how the business will need to operate in the future to meet the project objectives",
"To describe the processes and procedures required to manage uncertainty"
],
correct: 2,
explanation: [
"A. Incorrect. This describes the purpose of the issue management approach (formerly change control procedure), which governs how product changes are handled. See 11.2.1",
"B. Incorrect. This defines the quality management approach, which establishes which quality standards and procedures apply. See 8.2.1",
"C. Correct. The change management approach describes how the organizational shift and transition to the new way of working will be managed, so that the business can successfully adopt the targeted future state. See 3.4",
"D. Incorrect. This is the purpose of the risk management approach, which focuses on identifying and managing uncertainties (threats and opportunities). See 10.2.1"
]
},
{
exam: 1,
qnum: 15,
q: "A project holds a workshop to share experiences of new ways of working between project team members. Which principle is being applied by the people element?",
opts: [
"Learn from experience",
"Manage by exception",
"Define roles, responsibilities, and relationships",
"Focus on products"
],
correct: 0,
explanation: [
"A. Correct. Explicitly sharing and discussing lessons learned during an interactive workshop is a direct and people-centric implementation of the 'learn from experience' principle. See 2.2",
"B. Incorrect. 'Manage by exception' relates to direction via tolerances and escalations, which does not directly connect to a lessons workshop. See 2.4",
"C. Incorrect. This principle governs organization structure and who is responsible for what, not the proactive exchange of lessons learned. See 2.3",
"D. Incorrect. 'Focus on products' ensures that product requirements and quality remain central during planning and delivery, not the evaluation of team working methods. See 2.5"
]
},
{
exam: 1,
qnum: 16,
q: "Which management product must the project board approve to establish the project scope and timeframe?",
opts: [
"Project mandate",
"Benefits management approach",
"Project initiation documentation",
"Business case"
],
correct: 2,
explanation: [
"A. Incorrect. The project mandate is the trigger for the project, coming from the corporate layer, and does not yet contain a detailed, approved scope or schedule. See 14.3",
"B. Incorrect. The benefits management approach defines how and when the benefits of the project will be measured, not the scope and schedule of the project work itself. See 5.2.2",
"C. Correct. The Project Initiation Documentation (PID) aggregates all core plans and approaches. Approval of the PID by the project board marks the formal baseline for the scope, cost, and schedule of project execution. See 15.4",
"D. Incorrect. The business case provides the business justification (why, cost vs. benefits), but the detailed project scope and schedule are part of the broader PID (which includes the project plan). See 5.2.1, 15.4"
]
},
{
exam: 1,
qnum: 17,
q: "What is a purpose of the business case practice?",
opts: [
"To enable the project executive to decide whether to continue with the project",
"To identify the user's quality expectations to meet the business need",
"To prevent the planned outcomes from causing dis-benefits to the business",
"To define the products and how they will be delivered to satisfy the business case"
],
correct: 0,
explanation: [
"A. Correct. The purpose of the business case practice is to establish a mechanism that enables the executive (on behalf of the business) to continually assess whether the project is worth the investment and decide on its continuation. See 5.1",
"B. Incorrect. This belongs to the purpose of the 'quality' practice, which translates user needs and expectations into measurable criteria. See 8.1",
"C. Incorrect. Dis-benefits (negative side effects) can be inherent to a project; the business case identifies them to allow for a balanced decision, but cannot always simply 'prevent' them. See 5.2.1",
"D. Incorrect. This is primarily the purpose of the 'plans' practice (product-based planning), which maps out the required products and the delivery path. See 6.1"
]
},
{
exam: 1,
qnum: 18,
q: "Which should be used to justify whether the project should be progressed?",
opts: [
"Project brief and benefits management approach",
"Highlight report and benefits management approach",
"Business case and highlight report",
"Project brief and business case"
],
correct: 2,
explanation: [
"A. Incorrect. The project brief is used at the start of the project (in the starting up a project process) to gain permission to initiate, but not for ongoing justification during execution. See 14.4",
"B. Incorrect. The benefits management approach establishes how benefits are measured, but does not provide the current status summary and re-evaluated justification for the board. See 5.2.2",
"C. Correct. The business case contains the active business justification, and the highlight report gives the project board insight into progress within the current stage. Together, they enable the board to validate whether continuing is justified. See 5.1, 12.2.2",
"D. Incorrect. The project brief becomes functionally superseded once the PID and definitive business case are approved at the end of initiation. See 15.4"
]
},
{
exam: 1,
qnum: 19,
q: "Identify the missing words in the following sentence: A business objective concerns the measurable outcomes that demonstrate progress in relation to [?] to which the project must contribute.",
opts: [
"The strategy of the organization",
"The business's desired output",
"The business's desired benefits",
"The business justification"
],
correct: 0,
explanation: [
"A. Correct. Business objectives are strategic goals at the organizational level. Projects are initiated to deliver tangible contributions toward realizing the organization's strategy. See 5.1.1",
"B. Incorrect. Output is the direct physical or digital product delivered by the project, which is distinct from an overarching, measurable business objective. See 5.1.1",
"C. Incorrect. Benefits flow from the outcomes of the project, but the sentence specifically asks about the strategic framework (the strategy of the organization) to which the objectives are tied. See 5.1.1",
"D. Incorrect. The business justification is the specific evaluation for the project itself, not the broader context against which an organization-wide objective is measured. See 5.1"
]
},
{
exam: 1,
qnum: 20,
q: "A government department has a target to reduce its carbon footprint by 8-12%. How should this requirement be captured?",
opts: [
"As a benefits tolerance",
"As a sustainability tolerance",
"As outcomes to be achieved",
"As a quality tolerance"
],
correct: 1,
explanation: [
"A. Incorrect. A benefits tolerance relates to the margin around expected business benefits (e.g., revenue or savings), not specifically to environmental targets of the project outcome. See 5.4",
"B. Correct. Sustainability is one of the seven performance targets in PRINCE2 7. Setting a range (8-12%) for an environmental impact goal is the definition of applying a sustainability tolerance. See 12.1, 12.4",
"C. Incorrect. 'Outcomes to be achieved' is a general term for the effects of change, but does not describe the specific PRINCE2 control mechanism of the range. See 5.1.1",
"D. Incorrect. Quality tolerance defines acceptable deviation from product specifications (e.g., dimensions, speed), not the overarching sustainability performance of the project. See 8.4"
]
},
{
exam: 1,
qnum: 21,
q: "During a stage, the project manager recorded a new risk on the risk register. In which step of the business case management technique should its impact on the business case be assessed?",
opts: [
"Develop",
"Verify",
"Maintain",
"Confirm"
],
correct: 2,
explanation: [
"A. Incorrect. The 'develop' step takes place at the start of the project when the initial business case and assumptions are first formulated. See 5.3",
"B. Incorrect. 'Verify' relates to formal decision-making and checking by the project board at formal stage boundaries. See 5.3",
"C. Correct. The 'maintain' step involves continually updating the business case based on changes, issues, and newly identified risks that arise during the active stage. See 5.3",
"D. Incorrect. The 'confirm' step focuses on retroactively measuring and validating whether the intended benefits have actually been realized, often post-project. See 5.3"
]
},
{
exam: 1,
qnum: 22,
q: "The project manager has received feedback from stakeholders indicating that the structure of the project team should be changed. Which principle is being applied by the 'organization' practice when executing this feedback?",
opts: [
"Learn from experience",
"Define roles, responsibilities, and relationships",
"Manage by stages",
"Tailor to suit the project"
],
correct: 0,
explanation: [
"A. Correct. Responding to interim feedback and adjusting working methods or structure based on insights and experience gained is a direct application of the 'learn from experience' principle. See 2.2",
"B. Incorrect. This practice helps shape this principle, but the process of actively handling feedback to implement improvements is specifically linked to the learning principle. See 2.2, 2.3",
"C. Incorrect. 'Manage by stages' governs partitioning the project into manageable blocks of time, not the feedback and learning culture surrounding organization structure. See 2.7",
"D. Incorrect. 'Tailor to suit the project' ensures the method matches the initial project context, but continually optimizing via a feedback loop falls under learning from experience. See 2.6"
]
},
{
exam: 1,
qnum: 23,
q: "Which management product should specify individual accountability for sustainability targets?",
opts: [
"Role descriptions",
"Project management team structure",
"Product description",
"Business case"
],
correct: 0,
explanation: [
"A. Correct. To ensure that sustainability is effectively secured, specific duties and individual accountability for them must be explicitly included in the individual role descriptions of team members. See 5.2.3",
"B. Incorrect. The project management team structure provides a graphical or schematic overview of the hierarchy and lines within the team, but does not contain detailed individual duty and responsibility descriptions. See 5.2.3",
"C. Incorrect. A product description defines the characteristics, quality criteria, and required origin of a specific deliverable, not a person's responsibilities. See 6.2.1",
"D. Incorrect. The business case gives the overall financial and strategic justification for the project, including any project-level sustainability goals, but does not delegate this to an individual organizational level. See 5.2.1"
]
},
{
exam: 1,
qnum: 24,
q: "What is defined as having the authority to direct the project within the mandate of the business?",
opts: [
"Project manager",
"Project executive",
"Project management team",
"Project board"
],
correct: 3,
explanation: [
"A. Incorrect. The project manager has the authority to manage the project day-to-day within tolerances set by the project board, but does not direct the project at a strategic level. See 5.3.4",
"B. Incorrect. The executive is the key role within the project board and is ultimately accountable, but the collective authority to formally direct the project lies with the entire project board. See 5.3.1",
"C. Incorrect. The project management team encompasses the entire structure (board, PM, team managers), including executing roles that do not hold directing or mandating authority. See 5.1",
"D. Correct. The project board has the formal authority and responsibility to direct the project, make decisions, and grant approvals, operating within the boundaries set by the corporate layer. See 5.3.1"
]
},
{
exam: 1,
qnum: 25,
q: "How should the senior user fulfill their responsibility for the continued realization of benefits post-project?",
opts: [
"By representing the work needed in a hierarchy to help organize the project",
"By ensuring commitment from people in the user community to adopting the new products",
"By defining how to assure the continued justification of the project",
"By ensuring the technical integrity of the project products delivered to the users"
],
correct: 1,
explanation: [
"A. Incorrect. This describes creating a Product Breakdown Structure (PBS), which is a planning technique and not a specific governance activity of the senior user for the post-project phase. See 6.3",
"B. Correct. The senior user represents user interests and is responsible for product adoption in the line organization. Only through commitment and active adoption can the intended benefits be realized after the project ends. See 5.3.3",
"C. Incorrect. Assuring overall business justification is the primary duty of the project executive, not the senior user alone. See 5.3.2",
"D. Incorrect. Technical integrity and meeting supplier standards is the specific responsibility of the senior supplier. See 5.3.5"
]
},
{
exam: 1,
qnum: 26,
q: "A new team member has just joined the project team and is going on a site visit. In which step of the technique for organization design and development should this happen?",
opts: [
"Develop the project ecosystem",
"Understand the organizational ecosystem",
"Design the project ecosystem",
"Manage ongoing changes to the project ecosystem"
],
correct: 0,
explanation: [
"A. Correct. The 'develop the project ecosystem' step includes onboarding, training, and operationalizing the team, including activities like site visits to familiarize team members with the project environment. See 5.3",
"B. Incorrect. 'Understand the organizational ecosystem' focuses on analyzing the existing structures and culture of the parent organization beforehand, prior to assembling the team. See 5.3",
"C. Incorrect. 'Design the project ecosystem' involves determining the required roles, reporting lines, and meeting structures (the theoretical design). See 5.3",
"D. Incorrect. 'Manage ongoing changes' relates to handling turnover, movements, and structure adjustments during later stages of the project. See 5.3"
]
},
{
exam: 1,
qnum: 27,
q: "What is the purpose of the plans practice?",
opts: [
"To enable the project manager to control the project by defining who will deliver the products, and when to deliver them",
"To enable the project executive to monitor whether the project is desirable, viable and achievable and should continue",
"To allow the project executive to define which role in the project management team is responsible for producing the plan",
"To enable the project manager to plan how to respond to uncertainties, and who should execute the agreed measures"
],
correct: 0,
explanation: [
"A. Correct. The purpose of the plans practice is to provide realistic schedules and baselines that enable the project management team (specifically the PM) to control progress by establishing what is delivered, by whom, and when. See 6.1",
"B. Incorrect. This is the purpose of the business case practice in combination with progress control, not the primary purpose of the plans practice itself. See 5.1",
"C. Incorrect. Roles and responsibilities for planning are defined within the 'organization' practice and specific procedures, not as the main purpose of planning. See 5.1, 6.2",
"D. Incorrect. This describes risk response planning specifically, which is part of the 'risk' practice, though these measures are eventually integrated into plans. See 10.1"
]
},
{
exam: 1,
qnum: 28,
q: "The business strategy has changed, requiring the project scope to increase beyond the tolerances agreed by the corporate layer. Which plan must be created to incorporate this change?",
opts: [
"Project plan",
"Stage plan",
"Team plan",
"Exception plan"
],
correct: 3,
explanation: [
"A. Incorrect. The project plan shows total planning for the entire project. Although this plan may eventually be revised, the specific tool to handle a tolerance breach is an exception plan. See 6.2",
"B. Incorrect. A stage plan is the detailed operational planning for a specific stage, but cannot independently breach overarching tolerances of the corporate layer. See 6.2",
"C. Incorrect. A team plan is used by a team manager to manage work within a work package and is independent of strategic scope changes at the project level. See 6.2",
"D. Correct. When a forecast indicates that set tolerances (at project or stage level) will be exceeded, an exception plan must be prepared to show how the deviation will be recovered or processed. See 6.2, 12.4"
]
},
{
exam: 1,
qnum: 29,
q: "Identify the missing word in the following sentence: When planning, there are at least two types of [?] relevant to a project: internal and external.",
opts: [
"dependency",
"plans",
"exception",
"scope"
],
correct: 0,
explanation: [
"A. Correct. Identifying dependencies is crucial within PRINCE2 planning. Internal dependencies lie within the project's control; external dependencies involve relationships with other projects or the line organization. See 6.3",
"B. Incorrect. PRINCE2 features different levels of plans (project, stage, team), but this does not fit grammatically or conceptually with 'internal and external' in this context. See 6.2",
"C. Incorrect. An exception is a situation where tolerances are exceeded; this is not primarily split into fixed 'internal and external types' in planning definitions. See 12.4",
"D. Incorrect. Scope defines product and work boundaries, but specific relationships affecting sequence and scheduling are termed dependencies. See 6.3"
]
},
{
exam: 1,
qnum: 30,
q: "How should the project plan support an iterative-incremental project?",
opts: [
"By having multiple delivery stages allowing acceptance criteria to be refined as products are delivered",
"By ensuring that product descriptions are completed before the project is approved by the project board",
"By breaking down the work of the stage to the level of detail required for day-to-day control by the project manager",
"By dividing the project into two stages to allow iterative deliveries of products during the project"
],
correct: 0,
explanation: [
"A. Correct. In an iterative/incremental context (such as agile), the project plan uses sequential stages and timeboxes so criteria, feedback, and insights can be flexibly incorporated as working interim products emerge. See 6.2.1",
"B. Incorrect. Rigidly dictating that all detailed product descriptions must be 100% final upfront contradicts the philosophy of an iterative-incremental approach where scope evolves. See 6.2.1",
"C. Incorrect. Breaking work down to operational detail is the specific goal of a stage plan or team plan, not the primary strategic task of the over-arching project plan in an agile context. See 6.2.2",
"D. Incorrect. Artificially limiting a project to exactly two stages is not a general PRINCE2 guideline for iterative delivery; the number of stages depends on risks and control needs. See 6.2, 12.2"
]
},
{
exam: 1,
qnum: 31,
q: "The project manager must capture the user's quality expectations. In which step of the planning technique should these expectations be captured?",
opts: [
"Defining and analyzing the products",
"Organizing work packages",
"Estimating",
"Preparing a schedule"
],
correct: 0,
explanation: [
"A. Correct. The 'defining and analyzing the products' step (product-based planning) starts by creating the project product description, which explicitly captures the user's quality expectations and acceptance criteria. See 6.3",
"B. Incorrect. 'Organizing work packages' is a later step where actual execution tasks and mandates for teams are grouped and defined. See 6.3",
"C. Incorrect. 'Estimating' focuses on determining the effort, time, and cost needed based on defined product requirements. See 6.3",
"D. Incorrect. 'Preparing a schedule' involves setting out activities and milestones on a timeline, which can only happen once products and estimates are known. See 6.3"
]
},
{
exam: 1,
qnum: 32,
q: "What is a purpose of the quality practice?",
opts: [
"To enable control by defining how the project will deliver the products to satisfy the business case",
"To capture users' requirements and ensure they remain unchanged throughout the project",
"To identify how the project will ensure that users' requirements of the project products are met",
"To agree to deliver products that were not part of the business justification for the project"
],
correct: 2,
explanation: [
"A. Incorrect. This aligns with the purpose of the 'plans' practice, which structures paths and resources for product delivery. See 6.1",
"B. Incorrect. Requirements can and may change (via controlled change management). Quality management does not try to rigidly block change, but ensures what is delivered meets applicable standards. See 8.1, 11.1",
"C. Correct. The purpose of the quality practice is to specify quality expectations and criteria, and establish processes to demonstrate and ensure that delivered products meet those requirements. See 8.1",
"D. Incorrect. Products falling outside the business justification (scope creep) should not be added casually; every product must contribute to the business case. See 2.1, 2.5"
]
},
{
exam: 1,
qnum: 33,
q: "The team manager must record that a product needs to be tested, but has not yet been approved. Where should these details be recorded?",
opts: [
"Quality register",
"Quality specifications",
"Product register",
"Project product description"
],
correct: 0,
explanation: [
"A. Correct. The quality register tracks all planned and executed quality activities (such as tests, reviews, audits), including their status (e.g., 'planned', 'tested', 'approved'). See 8.2.3",
"B. Incorrect. Quality specifications are criteria the product must meet; this is a static part of a description, not a dynamic log for test statuses. See 8.2.1",
"C. Incorrect. The product register (or configuration item records) tracks product lifecycles and versions, but specific planning and outcomes of quality reviews belong in the quality register. See 11.2.3",
"D. Incorrect. The project product description defines the main project output at a high level and is created at the start; it is not an operational register for daily testing activities. See 6.2.1"
]
},
{
exam: 1,
qnum: 34,
q: "Which statement describes project assurance rather than quality assurance?",
opts: [
"It is independent of the project manager, but not independent of the project",
"It monitors the project's quality control metrics used to assess the project products",
"It is independent of the project team and may form part of the user's quality management system",
"It describes the agreed expectations for the project products"
],
correct: 0,
explanation: [
"A. Correct. Project assurance is the responsibility of project board members to check independently of the project manager that the project is being executed correctly, but it remains an internal project role. Quality assurance (corporate assurance) is completely external to the project. See 8.2.2",
"B. Incorrect. This relates to quality control and performing quality checks themselves, which is a duty of the project team/support, not the definition of project assurance. See 8.1",
"C. Incorrect. This describes external quality assurance at an organizational level (corporate/programme), which is fully independent of the temporary project organization. See 8.2.2",
"D. Incorrect. This describes the definition of quality expectations or acceptance criteria in a product description, not an assurance function. See 8.1"
]
},
{
exam: 1,
qnum: 35,
q: "A new requirement is identified when producing a subordinate plan. How should this be managed?",
opts: [
"By preparing new product descriptions",
"By using the issue management approach",
"By updating the project product description",
"By updating the quality management approach"
],
correct: 1,
explanation: [
"A. Incorrect. While a new product description may eventually be needed, this should not occur directly without first formally assessing impact via the issue procedure. See 11.1",
"B. Correct. Any new requirement, request, or change arising during the project is an issue (request for change). It must be recorded, assessed, and decided through the formal issue management approach. See 11.1, 11.2.1",
"C. Incorrect. The project product description is a baselined document; it must never be altered directly without an approved change via the issue procedure. See 11.1",
"D. Incorrect. The quality management approach describes general quality rules and methods for the project, not how a specific operational scope change is handled. See 8.2.1"
]
},
{
exam: 1,
qnum: 36,
q: "A system has been tested and the user needs to take ownership of it. In which step of the quality management technique should this happen?",
opts: [
"Gathering user inputs",
"Accepting products",
"Describing the quality management approach",
"Controlling quality"
],
correct: 1,
explanation: [
"A. Incorrect. 'Gathering user inputs' is the initial stage where requirements and expectations are collected, not the handover at the end. See 8.3",
"B. Correct. The 'accepting products' step within the quality technique involves formal clearance and handover of the tested and approved product to users/line organization, who thereby assume ownership. See 8.3",
"C. Incorrect. This concerns planning and establishing the quality strategy during initiation, not an operational product handover. See 8.2.1",
"D. Incorrect. 'Controlling quality' (quality control) focuses on performing tests and inspections to verify the product complies, prior to formal acceptance. See 8.3"
]
},
{
exam: 1,
qnum: 37,
q: "What is the purpose of the risk practice?",
opts: [
"To address concerns about standards that must be applied to products",
"To identify the probability of a threat occurring and its potential impact on the project",
"To guarantee that the agreed scope is delivered on time, within cost and quality",
"To ensure that problems are resolved before they have a chance to negatively impact the project"
],
correct: 1,
explanation: [
"A. Incorrect. This relates to quality or issue management, checking whether products meet agreed standards or if deviations exist. See 8.1, 11.1",
"B. Correct. The purpose of the risk practice is to systematically identify, assess, and control uncertainty during the project by mapping both probability (likelihood) and impact of threats (and opportunities). See 10.1",
"C. Incorrect. No practice can provide upfront guarantees; risk management minimizes probability of failure, but achieving goals is the task of overall project control. See 10.1",
"D. Incorrect. This is the purpose of issue management. A problem (issue) has already occurred, whereas a risk is an uncertain, future event. See 10.1, 11.1"
]
},
{
exam: 1,
qnum: 38,
q: "What provides the project management team with a guideline for capturing threats?",
opts: [
"Risk management approach",
"Risk register",
"Digital and data management approach",
"Work package description"
],
correct: 0,
explanation: [
"A. Correct. The risk management approach is the policy document prescribing guidelines, procedures, roles, and templates for how risks (threats and opportunities) must be identified and recorded within the project. See 10.2.1",
"B. Incorrect. The risk register is the actual environment or database where risks are logged, but the document providing the guideline and instructions for this is the approach. See 10.2.2",
"C. Incorrect. This document governs general data management, storage, and software tools, but does not contain specific risk management and escalation procedures. See 12.2.3",
"D. Incorrect. A work package description contains instructions for delivering specific products by a team, not project-wide risk guidelines. See 11.2.4"
]
},
{
exam: 1,
qnum: 39,
q: "Which term describes who is responsible for responding adequately to a risk?",
opts: [
"Risk owner",
"Risk actionee",
"Project support",
"Project assurance"
],
correct: 0,
explanation: [
"A. Correct. The risk owner is the person ultimately accountable for monitoring and managing a specific risk and ensuring that the selected response is effective. See 10.2.2",
"B. Incorrect. The risk actionee is the person assigned to physically execute the control measure under the direction of the risk owner. See 10.2.2",
"C. Incorrect. Project support provides administrative and supporting services (like maintaining the register), but carries no content responsibility for individual risk responses. See 5.3.6",
"D. Incorrect. Project assurance independently checks whether the risk management process is followed correctly, but does not manage the risks themselves. See 5.3.1"
]
},
{
exam: 1,
qnum: 40,
q: "How does loss aversion result in less effective decision-making when considering risks?",
opts: [
"By valuing the need to keep what you have, rather than gaining something new",
"By discounting the downside of the risk, believing that everything will go according to plan",
"By valuing the unity of the team rather than making the correct decision",
"By viewing risks with a greater probability of occurring as riskier"
],
correct: 0,
explanation: [
"A. Correct. Loss aversion is a psychological bias where people place disproportionately high value on retaining what they already possess (or the status quo), making them irrationally anxious about change and causing them to miss opportunities. See 10.3",
"B. Incorrect. This describes optimism bias or wishful thinking, where risks and negative indicators are incorrectly downplayed. See 10.3",
"C. Incorrect. This is the definition of groupthink, where harmony within the group is prioritized over critical, objective analysis. See 10.3",
"D. Incorrect. This is a rational risk assessment (probability x impact) and not an irrational cognitive misconception or decision-making error. See 10.3"
]
},
{
exam: 1,
qnum: 41,
q: "The project manager must understand the project environment and define how risk should be managed on the project. In which step of the risk management technique should this be defined?",
opts: [
"Identify",
"Assess",
"Plan",
"Implement"
],
correct: 0,
explanation: [
"A. Correct. The 'identify' step consists of two sub-steps: 'understand context' (establishing the project environment and risk approach) and subsequently 'identify risks'. See 10.3",
"B. Incorrect. 'Assess' focuses on estimating the probability, impact, and proximity of already discovered, specific risks. See 10.3",
"C. Incorrect. 'Plan' involves selecting and preparing specific risk responses (such as avoid, transfer, or accept). See 10.3",
"D. Incorrect. 'Implement' ensures that planned risk measures are actively executed and monitored. See 10.3"
]
},
{
exam: 1,
qnum: 42,
q: "How does the issues practice contribute to a successful project?",
opts: [
"By identifying events that can have a positive impact on the project objectives",
"By controlling modifications to the current approved versions of management products",
"By adjusting the required approval level to match the expectations of the user",
"By making an uncertain situation certain by addressing its cause"
],
correct: 1,
explanation: [
"A. Incorrect. This describes identifying opportunities, which is a specific part of the 'risk' practice, not issue management. See 10.1",
"B. Correct. The issues practice (change and issue management) ensures stability by safeguarding that no unauthorized changes occur on baselined products and that modifications are controlled. See 11.1",
"C. Incorrect. Determining approval levels (governance) is set up based on tolerances and roles, not dynamically adjusted to changing user expectations during issue management. See 5.1, 11.2.1",
"D. Incorrect. Issue management handles actual events and problems that are already occurring; it cannot magically make the future 'certain', but controls change impact. See 11.1"
]
},
{
exam: 1,
qnum: 43,
q: "Project support must understand how changes can be made to approved versions of the project products. Which management product should project support review?",
opts: [
"Issue management approach",
"Risk management approach",
"Benefits management approach",
"Quality management approach"
],
correct: 0,
explanation: [
"A. Correct. The issue management approach outlines specific procedures, escalation lines, and rules for submitting, assessing, and authorizing changes to baselined products. See 11.2.1",
"B. Incorrect. The risk management approach provides instructions on handling uncertainties, threats, and opportunities, not on the actual change control of products. See 10.2.1",
"C. Incorrect. The benefits management approach governs how and when project benefits are measured and reported post-project. See 5.2.2",
"D. Incorrect. The quality management approach sets standards and testing procedures, but administrative change procedures fall under issue management. See 8.2.1"
]
},
{
exam: 1,
qnum: 44,
q: "What is the definition of an issue?",
opts: [
"A relevant event for the project that the project management must take into account",
"An uncertain event or set of events that, if it should happen, would have an effect on the project",
"A description of the impact that an uncertain event would have on the objectives",
"A measurable threshold to reflect the acceptable range of outcomes for each impacted objective"
],
correct: 0,
explanation: [
"A. Correct. Within PRINCE2, an issue is defined as any relevant event that has already happened, was not planned, and requires project management attention (such as a problem, request for change, or off-specification). See 11.1",
"B. Incorrect. This is the formal definition of a risk (uncertain, future-focused), not an active issue. See 10.1",
"C. Incorrect. This is the definition of a risk impact analysis or description of a risk effect, not an issue. See 10.1",
"D. Incorrect. This is the definition of a tolerance or threshold value belonging to the 'progress' practice. See 12.1"
]
},
{
exam: 1,
qnum: 45,
q: "A change has been approved and needs to be implemented. Which part of the guidance for effective issue management should enable the implementation of the change?",
opts: [
"Delegation of authority to the correct level by the project board to decide on changes",
"Application of the change budget within allowed constraints to make trade-offs",
"Audit of whether the actual status of the product matches the status recorded in the product register",
"Definition of the correct level at which products must be baselined"
],
correct: 1,
explanation: [
"A. Incorrect. Delegating authority (like to a change authority) helps with deciding on a change, but not directly with financial or practical realization and trade-offs of implementation itself. See 11.3",
"B. Correct. Having and applying a specific change budget enables the project to fund extra costs of approved changes directly without drawing on active stage tolerances. See 11.3",
"C. Incorrect. A status audit verifies retroactively that administration is correct (configuration management), but is not the mechanism activating change implementation funding. See 11.3",
"D. Incorrect. Determining baseline levels (configuration items) governs product management structure, not the action of implementing a new change. See 11.3"
]
},
{
exam: 1,
qnum: 46,
q: "An issue has been identified and its impact on the project scope needs to be understood. In which step of the issue management technique should its impact be understood?",
opts: [
"Assess issues",
"Capture issues",
"Decide on changes",
"Implement changes"
],
correct: 0,
explanation: [
"A. Correct. In the 'assess issues' step, the project manager performs a detailed impact analysis to understand consequences of the issue for scope, schedule, cost, risk, and business case. See 11.3",
"B. Incorrect. 'Capture issues' is merely the initial step where the issue is formally received, categorized, and logged in the issue register. See 11.3",
"C. Incorrect. 'Decide on changes' follows assessment; here the appropriate authority (PM or board) selects the best response based on impact analysis. See 11.3",
"D. Incorrect. 'Implement changes' is the final step where the approved solution is physically executed. See 11.3"
]
},
{
exam: 1,
qnum: 47,
q: "What is the purpose of the progress practice?",
opts: [
"To forecast whether the stage is on track to be delivered on time and within budget",
"To record information so that past mistakes can be avoided by this project or other projects",
"To decide what to do with a product that does not meet quality specifications",
"To ensure that user's quality expectations are met when delivering the output"
],
correct: 0,
explanation: [
"A. Correct. The purpose of the progress practice is to establish a control and reporting structure to continually compare actual performance against plans and forecast whether targets will be met within tolerances. See 12.1",
"B. Incorrect. This describes the learning process (learning from experience) and maintaining the lessons log, not the primary focus of progress control. See 2.2",
"C. Incorrect. This falls under handling deviations (quality/issues), like managing an off-specification, not general progress measurement. See 11.1",
"D. Incorrect. This is the specific objective of the 'quality' practice and quality control, not overall progress administration. See 8.1"
]
},
{
exam: 1,
qnum: 48,
q: "What must the project board review when deciding what should happen next with the project?",
opts: [
"Digital and data management approach",
"End stage report",
"Highlight report",
"Checkpoint report"
],
correct: 1,
explanation: [
"A. Incorrect. This is a facilitative document about data structures and systems, providing no performance evaluation of a completed stage. See 12.2.3",
"B. Correct. At the end of a management stage, the project manager provides the project board with an end stage report. This report offers a comprehensive view of performance and enables the board to decide on decharge and whether to start the next stage. See 12.2.2, 18.4",
"C. Incorrect. A highlight report is sent periodically during an active stage to keep the board informed, not as a decision document at a formal stage boundary. See 12.2.2",
"D. Incorrect. A checkpoint report is an operational progress report from a team manager to the project manager and does not go directly to the project board. See 12.2.2"
]
},
{
exam: 1,
qnum: 49,
q: "What is the definition of an exception?",
opts: [
"A forecast that agreed tolerance levels will be exceeded",
"An uncertain event that, if it should happen, would have an effect on achieving objectives",
"A product that does not meet quality specifications",
"A report to the project manager on the status of the work package"
],
correct: 0,
explanation: [
"A. Correct. Within PRINCE2, an exception occurs when there is a realistic forecast or actual situation where agreed tolerance boundaries (for time, cost, scope, etc.) are at risk of being exceeded. See 12.1, 12.4",
"B. Incorrect. This is the definition of a risk, not an exception. See 10.1",
"C. Incorrect. This defines a product defect or an issue (off-specification), not the process status of an exception situation. See 11.1",
"D. Incorrect. This describes a checkpoint report, which is a progress tool and not an exception itself. See 12.2.2"
]
},
{
exam: 1,
qnum: 50,
q: "How should the use of data and systems effectively support progress management?",
opts: [
"By focusing the project management team's efforts on gathering data about what happened in the past",
"By providing accurate data that helps in forecasting future project performance",
"By focusing the project management team's efforts on manual data collection",
"By defining tolerances against the seven performance targets for each management level"
],
correct: 1,
explanation: [
"A. Incorrect. Only looking backward (historical data) is insufficient; effective progress management uses data to look proactively at the future. See 12.2.3",
"B. Correct. Leveraging digital systems and analytics provides reliable data, essential for recognizing trends and making accurate forecasts about future project performance. See 12.2.3",
"C. Incorrect. Manual collection is error-prone and inefficient; systems should reduce administrative burdens via automation. See 12.2.3",
"D. Incorrect. Defining tolerances is a governance action at the start of a stage/project and is not the operational way data and systems support ongoing measurements. See 12.4"
]
},
{
exam: 1,
qnum: 51,
q: "At which level, according to the management technique for exceptions, is the likelihood HIGHEST that projects identify issues that exceed stage tolerances?",
opts: [
"Commissioning AND directing",
"Directing AND managing",
"Directing AND delivering",
"Managing AND delivering"
],
correct: 3,
explanation: [
"A. Incorrect. The commissioning (corporate) and directing (board) levels are too far removed from day-to-day operations to be first to signal operational exceptions. See 12.4",
"B. Incorrect. Directing is the board level; they receive escalations but rarely identify them themselves on the ground. See 12.4",
"C. Incorrect. Directing is the board level, which is not where daily progress and work package exceptions directly emerge. See 12.4",
"D. Correct. The 'managing' (project manager) and 'delivering' (team managers and specialists) levels are closest to daily execution of work and work packages. Here, operational issues and threatening tolerance breaches are logically discovered first. See 12.4"
]
},
{
exam: 1,
qnum: 52,
q: "What is a purpose of the 'starting up a project' process?",
opts: [
"To assess whether a project is likely to be worthwhile for the organization",
"To analyze the work required before the project initiation documentation is implemented",
"To give users the opportunity to confirm that they accept the project product",
"To delegate management of the project in a controlled manner"
],
correct: 0,
explanation: [
"A. Correct. The main purpose of the 'starting up a project' process is to filter and establish whether the project proposal is viable and worthwhile, preventing the organization from incurring unnecessary costs for an extensive initiation stage. See 14.1",
"B. Incorrect. Detailed planning and analysis of project setup occurs after approval, within the 'initiating a project' process where the PID is produced. See 15.1",
"C. Incorrect. Formal user acceptance of final products takes place at the end of the project within the 'closing a project' process, not at initial startup. See 19.1",
"D. Incorrect. Delegating and establishing detailed tolerances occurs stage-by-stage during project execution, not during pre-project activities. See 12.4, 13.1"
]
},
{
exam: 1,
qnum: 53,
q: "Which process should ensure that an organization does not proceed to establish solid foundations for unsuitable projects?",
opts: [
"Starting up a project",
"Directing a project",
"Initiating a project",
"Managing a stage boundary"
],
correct: 0,
explanation: [
"A. Correct. The 'starting up a project' process acts as a gatekeeper. It prevents expensive resources and time from being wasted on initiating ('laying solid foundations for') projects that are inherently unsuitable or unachievable. See 14.1",
"B. Incorrect. Although the project board makes the decision via 'directing', the specific process designed to execute and support this pre-project check is 'starting up a project'. See 14.1, 15.1",
"C. Incorrect. Within 'initiating', the solid foundations are actually laid (the PID). This process starts only after the initial suitability check in 'starting up' is complete. See 15.1",
"D. Incorrect. 'Managing a stage boundary' is used during execution to govern the transition between sequential stages, long after initial project selection. See 18.1"
]
},
{
exam: 1,
qnum: 54,
q: "What is a purpose of the 'directing a project' process?",
opts: [
"To retain accountability of the project board while delegating detailed management",
"To prevent the organization from executing projects with poor justification",
"To manage the work of a stage by implementing effective corrective measures",
"To provide information so that the commissioning authority can commit to project delivery"
],
correct: 0,
explanation: [
"A. Correct. The purpose of 'directing a project' is to enable the project board to retain over-arching responsibility and provide direction, while day-to-day management is fully delegated to the project manager. See 13.1",
"B. Incorrect. This is primarily the purpose of the 'starting up a project' process, which filters based on initial business justification. See 14.1",
"C. Incorrect. Managing a stage and taking corrective operational measures is the specific operational duty of the project manager within 'controlling a stage'. See 16.1",
"D. Incorrect. Providing information on project setup so the organization can agree is an objective of the 'initiating a project' process. See 15.1"
]
},
{
exam: 1,
qnum: 55,
q: "Which TWO are objectives of the 'controlling a stage' process?\n1. To ensure that there are no uncontrolled changes to the products agreed by the project board\n2. To ensure that the project board can be certain that all products in the stage plan are completed\n3. To ensure that the project initiation documentation is updated with all quality changes required for the next project stage\n4. To ensure that products delivered in the stage meet agreed quality criteria",
opts: [
"1 and 2",
"2 and 3",
"3 and 4",
"1 and 4"
],
correct: 3,
explanation: [
"A. Incorrect. Statement 2 is incorrect for this process: convincing the project board that the stage is fully completed and preparing for the future occurs specifically in the 'managing a stage boundary' process, not in 'controlling a stage'. See 16.2, 18.2",
"B. Incorrect. Both statement 2 (see above) and statement 3 are incorrect. Structurally updating the PID for the next stage belongs to stage boundary planning. See 18.2",
"C. Incorrect. Statement 3 is incorrect. Statement 4 is correct: monitoring product quality within the active stage is a core objective of 'controlling a stage'. See 16.2",
"D. Correct. Within 'controlling a stage', the PM focuses on preventing scope creep (statement 1) and ensuring that active products in the stage meet specified quality requirements (statement 4). See 16.2"
]
},
{
exam: 1,
qnum: 56,
q: "Which TWO are objectives of the 'directing a project' process?\n1. To ensure that the project is closed only with appropriate authorization\n2. To ensure that post-project benefits reviews are planned\n3. To ensure that the business is ready to use the products after project closure\n4. To ensure that users have accepted the project product",
opts: [
"1 and 2",
"2 and 3",
"3 and 4",
"1 and 4"
],
correct: 0,
explanation: [
"A. Correct. The 'directing a project' process ensures the project board maintains control over vital lifelines: they must authorize formal closure (statement 1) and oversee planning for post-project benefits measurements (statement 2). See 13.2",
"B. Incorrect. Statement 3 is an operational preparation task executed within the 'closing a project' process by the project manager and the line, not a direct governance objective of 'directing'. See 19.2",
"C. Incorrect. Both statement 3 and statement 4 fall under responsibilities and objectives of the executing process 'closing a project'. See 19.2",
"D. Incorrect. Statement 4 (obtaining user acceptance) is physically organized and checked within the 'closing a project' process by the PM, before the project board confirms it. See 19.2"
]
},
{
exam: 1,
qnum: 57,
q: "Which TWO are objectives of the 'initiating a project' process?\n1. To ensure that the project team focuses on delivering the approved products in the stage plan\n2. To ensure that the project team is authorized to proceed to the initiation stage\n3. To understand how changes to agreed project products are approved\n4. To prepare a schedule and estimates of costs for work to deliver the products",
opts: [
"1 and 2",
"2 and 3",
"3 and 4",
"1 and 4"
],
correct: 2,
explanation: [
"A. Incorrect. Statement 1 belongs to 'controlling a stage' during execution. Statement 2 is incorrect: authority to start initiation is granted at the end of 'starting up a project'. See 14.2, 16.2",
"B. Incorrect. Statement 2 is incorrect (see above). Statement 3 is correct: during the initiation stage, the issue management procedure (change control) is established. See 15.2",
"C. Correct. The 'initiating a project' process establishes baselines. Objectives include agreeing change authorities (statement 3) and delivering the project plan with cost and time estimates (statement 4). See 15.2",
"D. Incorrect. Statement 1 is incorrect for this process (belongs to the later execution phase), though statement 4 describes a core output of initiation. See 15.2, 16.2"
]
},
{
exam: 1,
qnum: 58,
q: "Which activity can ONLY be performed in the 'managing a stage boundary' process?",
opts: [
"Preparing a replacement for the current stage plan for approval by the project board",
"Continually reviewing the business justification against the business case",
"Regularly reporting the progress of a stage to the project board",
"Preparing a premature closure of the project after direction by the project board"
],
correct: 0,
explanation: [
"A. Correct. Preparing a new stage plan (or an exception plan to replace an escalating plan) to request approval for the next step is the unique and exclusive activity of the 'managing a stage boundary' process. See 18.3",
"B. Incorrect. Re-evaluating and reviewing the business case happens across multiple processes (such as 'controlling a stage' at every issue and 'directing a project'), and is not exclusive to stage boundaries. See 5.3, 16.3",
"C. Incorrect. Progress reporting (highlight reports) occurs continually during execution within the 'controlling a stage' process. See 16.3",
"D. Incorrect. If a project is closed prematurely, the board instructs the PM to move directly to the 'closing a project' process. Preparing that closure occurs there, not in a regular stage boundary. See 19.3"
]
},
{
exam: 1,
qnum: 59,
q: "What is required to execute the 'managing a stage boundary' process?",
opts: [
"The work of the project must be divided into sections",
"Each project stage must incrementally deliver project benefits",
"The project must have a predictable end date",
"Every stage must be in exception"
],
correct: 0,
explanation: [
"A. Correct. To apply this process at all, the project must be divided into at least two manageable blocks of time or sections (management stages) in line with the 'manage by stages' principle. Without this division, there are no stage boundaries to manage. See 2.7, 18.1",
"B. Incorrect. It is a bonus if a project delivers benefits early (incremental delivery), but this is not a hard process requirement to run a formal management stage boundary. See 5.1",
"C. Incorrect. Particularly in unpredictable or innovative projects, dividing into stages helps control risks; an exact predictable end date is not a prerequisite for the process. See 2.7",
"D. Incorrect. This process is primarily run at the end of each successful and regular stage. It is only used for an exception plan during escalations, so certainly not 'every stage must be in exception'. See 18.1"
]
},
{
exam: 1,
qnum: 60,
q: "Which action must be taken if a project is closed prematurely?",
opts: [
"The project manager must still use the 'closing a project' process to deal with the situation",
"The project manager must ensure that no extra work is carried out before the project is closed",
"The project manager must trigger the premature closure if the business case is no longer valid",
"The project board must approve the use of the remaining project budget to fund operational costs"
],
correct: 0,
explanation: [
"A. Correct. Even if a project is stopped halfway by the project board, it must be decommissioned orderly. The PM must still go through the 'closing a project' process to document status, secure products, and release resources. See 19.3",
"B. Incorrect. An orderly closure may require *temporary extra work*, such as safeguarding data, handing over semi-finished products, or closing supplier contracts. See 19.2",
"C. Incorrect. The project manager advises and signals, but formal authority to trigger and decide on premature closure rests exclusively with the project board. See 19.3",
"D. Incorrect. The board governs project funding, but allocating remaining budgets for regular line operational costs (business as usual) falls under corporate governance and is not a standard action within the PRINCE2 project closure process. See 19.3"
]
},
{
exam: 2,
qnum: 1,
q: "Which is one of the five integrated elements of PRINCE2?",
opts: [
"The project brief",
"The project context",
"The project plan",
"The business case"
],
correct: 1,
explanation: [
"A. Incorrect. The project brief is a management product produced during the 'starting up a project' process, not one of the five integrated elements. See 1.2, 14.4",
"B. Correct. The project context is one of the five integrated elements of PRINCE2 (along with people, principles, practices, and processes). It emphasizes that PRINCE2 must be tailored to suit the specific environment of the project. See 1.2",
"C. Incorrect. The project plan is a management product within the plans practice, not a core integrated element of the method. See 1.2, 6.2",
"D. Incorrect. The business case is a practice and a management product, but not one of the five overarching integrated elements. See 1.2, 5.1"
]
},
{
exam: 2,
qnum: 2,
q: "Which statement about the 'focus on products' principle is CORRECT?",
opts: [
"A PRINCE2 project focuses on the activities required to deliver the project's products",
"Product-based planning ensures that the project team is clear about what needs to be delivered",
"A project product description is only required for the final deliverable of the project",
"The project board must approve every product description before work on it can begin"
],
correct: 1,
explanation: [
"A. Incorrect. A PRINCE2 project focuses on the definition and delivery of products, first and foremost, rather than the activities themselves. Activities are derived from the products. See 2.5",
"B. Correct. The 'focus on products' principle ensures that all stakeholders have a shared understanding of what the project will deliver and its quality criteria. Product-based planning supports this directly. See 2.5",
"C. Incorrect. Product descriptions are created for all major products and components within a project, not just the final end product. See 2.5, 6.3",
"D. Incorrect. The project board approves the overarching project product description and major plans, but authority for individual product descriptions can be delegated or handled by the project manager. See 2.4, 5.3"
]
},
{
exam: 2,
qnum: 3,
q: "Which is a responsibility of the 'people' element in a PRINCE2 project?",
opts: [
"To ensure that all stakeholders are managed in exactly the same way",
"To understand the relationships between individuals and teams within the project ecosystem",
"To establish the precise financial constraints for the project's sustainability targets",
"To define the specific sequence of activities in the stage plan"
],
correct: 1,
explanation: [
"A. Incorrect. Stakeholders have different needs and must be engaged appropriately based on their specific context, not in exactly the same way. See 3.1",
"B. Correct. The people element focuses on how individuals work together, communication, leadership, and understanding the relationships across the project ecosystem to foster collaboration. See 3.1",
"C. Incorrect. Setting financial and sustainability constraints belongs to the business case and progress practices, not the people element. See 5.4, 12.1",
"D. Incorrect. Sequencing activities is a technical step within the planning technique of the plans practice. See 6.3"
]
},
{
exam: 2,
qnum: 4,
q: "A project manager is tailoring PRINCE2 for a small, low-risk project by combining roles and simplifying management products. Which principle is being applied?",
opts: [
"Manage by stages",
"Manage by exception",
"Tailor to suit the project",
"Define roles, responsibilities, and relationships"
],
correct: 2,
explanation: [
"A. Incorrect. 'Manage by stages' relates to partitioning the project into management intervals, not adapting the roles or products to the project size. See 2.7",
"B. Incorrect. 'Manage by exception' is about delegating authority through setting performance tolerances, not scaling the method's complexity. See 2.4",
"C. Correct. The 'tailor to suit the project' principle explicitly ensures that the PRINCE2 method is adapted to the scale, complexity, geography, and risk of the project so that management effort matches the risk. See 2.6",
"D. Incorrect. While roles are being combined, the act of scaling and adapting the overall framework to the project's small size is driven by the tailoring principle. See 2.3, 2.6"
]
},
{
exam: 2,
qnum: 5,
q: "What is a characteristic of effective project leadership within the PRINCE2 method?",
opts: [
"It relies purely on transactional command-and-control management structures",
"It avoids seeking feedback from stakeholders to maintain direction",
"It adapts to the needs of the team and the specific phase of the project lifecycle",
"It is solely the responsibility of the project executive"
],
correct: 2,
explanation: [
"A. Incorrect. PRINCE2 7 promotes modern leadership that emphasizes collaboration, persuasion, and co-creation over rigid, old-fashioned command-and-control mechanisms. See 3.3",
"B. Incorrect. Effective leaders actively seek feedback to ensure alignment, maintain motivation, and foster continuous improvement. See 3.3",
"C. Correct. Leadership must be situational; a good project leader adapts their style, communication, and approach depending on the maturity of the team and the current needs of the lifecycle phase. See 3.1, 3.3",
"D. Incorrect. Leadership is exercised across all layers of the project management team, including the project manager and team managers, not just by the executive. See 5.1"
]
},
{
exam: 2,
qnum: 6,
q: "What is the primary objective of organizational change management in a PRINCE2 project?",
opts: [
"To control and log modifications made to the technical product baselines",
"To support the people impacted by the project to transition to new ways of working",
"To establish the reporting schedule for checkpoint reports",
"To ensure that the project plan remains within its original cost tolerances"
],
correct: 1,
explanation: [
"A. Incorrect. Controlling modifications to baselines is configuration management, which is part of the issues practice. See 11.1",
"B. Correct. Change management (organizational change) focuses on the human side of change, ensuring that people understand, accept, and effectively adopt the new capabilities delivered by the project. See 3.4",
"C. Incorrect. Setting up reporting frequencies for team managers belongs to progress management and work package administration. See 12.2, 16.3",
"D. Incorrect. Maintaining cost tolerances is part of progress and financial control, not organizational change management. See 12.1"
]
},
{
exam: 2,
qnum: 7,
q: "Which statement best describes the relationship between project outputs and outcomes?",
opts: [
"Outputs are the strategic goals, while outcomes are the physical products",
"Outputs are delivered by the project, and outcomes are the result of using those outputs",
"Outcomes must always be fully realized before any outputs can be delivered",
"Outputs are evaluated post-project, while outcomes are managed day-to-day by team managers"
],
correct: 1,
explanation: [
"A. Incorrect. This is reversed: outputs are the tangible or intangible products, whereas outcomes are the changes resulting from their use. See 5.1.1",
"B. Correct. An output is a specialist product handed over by the project. An outcome is the change in behavior or operational environment achieved when users actually use that output. See 5.1.1",
"C. Incorrect. Outcomes occur after outputs are delivered and put into service; they cannot be realized before the outputs exist. See 5.1.1",
"D. Incorrect. Outputs are managed day-to-day and delivered during the project. Outcomes typically develop as the outputs are used, often extending beyond the project boundary. See 5.1.1"
]
},
{
exam: 2,
qnum: 8,
q: "What is the main purpose of the benefits management approach?",
opts: [
"To justify the total financial cost of the initiation stage",
"To define how and when the realization of project benefits will be measured and reviewed",
"To serve as a contract between the senior supplier and the external market",
"To keep a log of all risks that might negatively impact the project schedule"
],
correct: 1,
explanation: [
"A. Incorrect. The business case justifies the overall investment, but the benefits management approach specifically addresses the tracking mechanism for benefits, not just initiation costs. See 5.2.2",
"B. Correct. The benefits management approach defines the actions, timelines, and responsibilities for verifying whether the intended benefits are achieved, both during and after the project. See 5.2.2",
"C. Incorrect. It is an internal management product used for project governance, not a commercial contract with external suppliers. See 5.2.2",
"D. Incorrect. Risks are recorded and tracked in the risk register, which is part of the risk practice. See 10.2.2"
]
},
{
exam: 2,
qnum: 9,
q: "Who is ultimately accountable for the project's success and for ensuring that the investment has continuous business justification?",
opts: [
"The project manager",
"The senior user",
"The project executive",
"The project support role"
],
correct: 2,
explanation: [
"A. Incorrect. The project manager is responsible for day-to-day management within tolerances, but is not ultimately accountable for the business investment itself. See 5.3.4",
"B. Incorrect. The senior user is accountable for the quality and adoption of user products and user benefits, but the executive holds ultimate overall accountability. See 5.3.2, 5.3.3",
"C. Correct. The project executive represents the business interest and owns the business case. They are ultimately accountable for the project's success and ensuring it remains a justified investment. See 5.3.2",
"D. Incorrect. Project support provides administrative assistance and has no decision-making or governance accountability. See 5.3.6"
]
},
{
exam: 2,
qnum: 10,
q: "Which product-based planning document provides a detailed description of a specific product's purpose, composition, derivation, and quality criteria?",
opts: [
"Product breakdown structure",
"Product description",
"Product flow diagram",
"Project plan"
],
correct: 1,
explanation: [
"A. Incorrect. A product breakdown structure (PBS) is a hierarchical diagram showing all the products to be delivered, but it does not contain detailed text descriptions for individual products. See 6.3",
"B. Correct. A product description is a dedicated management product created to define exactly what a product is, what it is made of, where it comes from, and the quality tests it must pass. See 6.2.1, 6.3",
"C. Incorrect. A product flow diagram (PFD) shows the sequence and dependencies of product creation, not the detailed characteristics of a single product. See 6.3",
"D. Incorrect. The project plan provides a high-level timeline, resource overview, and budget for the whole project, but relies on individual product descriptions for specific asset details. See 6.2"
]
},
{
exam: 2,
qnum: 11,
q: "What type of dependency exists when the sequence of project activities is dictated by a factor completely outside the control of the project team?",
opts: [
"Internal dependency",
"External dependency",
"Flexible dependency",
"Subordinate dependency"
],
correct: 1,
explanation: [
"A. Incorrect. An internal dependency is an interaction between two activities or products that both fall inside the direct control of the project team. See 6.3",
"B. Correct. An external dependency involves an interface with an entity or activity outside the project's boundary (e.g., legislation updates, a separate project's deliverable) that the project team cannot directly control. See 6.3",
"C. Incorrect. 'Flexible' is not a standard PRINCE2 classification for project plan dependencies. See 6.3",
"D. Incorrect. 'Subordinate' is not a term used by PRINCE2 to define the primary types of scheduling dependencies. See 6.3"
]
},
{
exam: 2,
qnum: 12,
q: "Which practice has the explicit purpose of establishing mechanisms to verify that products are 'fit for purpose' and meet the customer's expectations?",
opts: [
"Plans practice",
"Issues practice",
"Quality practice",
"Progress practice"
],
correct: 2,
explanation: [
"A. Incorrect. The plans practice focuses on schedules, timelines, and resource allocation. See 6.1",
"B. Incorrect. The issues practice focuses on managing requests for change, problems, and configuration management. See 11.1",
"C. Correct. The purpose of the quality practice is to ensure that the project's products meet the specified criteria and are fully capable of achieving their intended objectives. See 8.1",
"D. Incorrect. The progress practice focuses on monitoring performance against targets and managing tolerances. See 12.1"
]
},
{
exam: 2,
qnum: 13,
q: "Where should the project manager log information about planned quality reviews, their assigned reviewers, and the actual dates they were completed?",
opts: [
"Quality register",
"Risk register",
"Daily log",
"Issue register"
],
correct: 0,
explanation: [
"A. Correct. The quality register is the dynamic operational log used to track all quality activities (inspections, tests, reviews) throughout the lifecycle of the project. See 8.2.3",
"B. Incorrect. The risk register tracks uncertainties that have not yet occurred, not the status of planned quality tests. See 10.2.2",
"C. Incorrect. The daily log handles informal notes or minor events that do not require formal structure, whereas quality activities require dedicated tracking in the quality register. See 12.2.2",
"D. Incorrect. The issue register tracks active problems, defects (off-specifications), and change requests, not the calendar schedule of normal quality assurance reviews. See 11.2.2"
]
},
{
exam: 2,
qnum: 14,
q: "What is an 'off-specification' within PRINCE2 issue management?",
opts: [
"A product that has been delivered ahead of schedule and under budget",
"Something that the project should provide but currently does not, or is forecast not to meet its specifications",
"A change to a project management role description that requires corporate approval",
"A risk that has an exceptionally high probability of occurrence"
],
correct: 1,
explanation: [
"A. Incorrect. Delivering a product early is a positive variance or milestone achievement, not a technical non-conformance. See 11.1, 12.1",
"B. Correct. An off-specification is a specific type of issue representing a defect or shortfall: a product fails to meet its quality criteria or a requirement is missing from what was originally baseline-agreed. See 11.1",
"C. Incorrect. This is an organizational change or governance adjustment, not a product non-conformance. See 5.1",
"D. Incorrect. An off-specification is an active, factual issue that has already happened or is definitely forecast, not an uncertain future event (risk). See 10.1, 11.1"
]
},
{
exam: 2,
qnum: 15,
q: "Which step in the PRINCE2 risk management technique involves determining the proximity of a threat and calculating its combined probability and impact?",
opts: [
"Identify risks",
"Assess risks",
"Plan responses",
"Implement responses"
],
correct: 1,
explanation: [
"A. Incorrect. 'Identify risks' focuses on discovering and explicitly describing the threats and opportunities, not calculating their mathematical weights. See 10.3",
"B. Correct. The 'assess risks' step evaluates each identified risk to understand its likelihood, expected timing (proximity), and potential severity of impact on project objectives. See 10.3",
"C. Incorrect. 'Plan responses' focuses on formulating strategies (like avoid, mitigate, or transfer) to handle the risk once its severity is known. See 10.3",
"D. Incorrect. 'Implement' involves assigning the actions and ensuring that the selected risk controls are actively carried out. See 10.3"
]
},
{
exam: 2,
qnum: 16,
q: "If a project manager forecasts that the current stage cost will exceed its allowed cost tolerance, what action MUST they take?",
opts: [
"Immediately adjust the project plan baseline without informing the board",
"Raise an issue and escalate the situation by submitting an exception report to the project board",
"Instruct the team managers to stop all quality verification tests to save money",
"Ask project support to delete the over-budget entries from the financial system"
],
correct: 1,
explanation: [
"A. Incorrect. A project manager does not have the authority to unilaterally change baselines when tolerances are breached. This violates the 'manage by exception' principle. See 2.4, 12.4",
"B. Correct. When a tolerance deviation is forecast or occurs, it creates an exception. The project manager must document this in an exception report and escalate it to the project board for a decision. See 12.4",
"C. Incorrect. Skipping quality tests violates the 'focus on products' principle and increases project risk, making it an unacceptable hidden action. See 2.5, 8.1",
"D. Incorrect. Manipulating data or registers is unethical and defeats the purpose of progress control and transparency. See 12.2.3"
]
},
{
exam: 2,
qnum: 17,
q: "What is the primary role of a 'change authority' in a project?",
opts: [
"To retrain operational staff on new software interfaces",
"To review and approve or reject specific requests for change and off-specifications",
"To write the project brief during pre-project preparation",
"To audit the financial compliance of the corporate board"
],
correct: 1,
explanation: [
"A. Incorrect. This is a training or change management execution task, not a governance role for approving scope modifications. See 3.4",
"B. Correct. To avoid overloading the project board with minor change requests, the board can delegate authority to a change authority to review and rule on changes within an allocated change budget. See 11.2.1, 11.3",
"C. Incorrect. The project brief is typically provided by corporate commissioning or drafted by the project manager during the startup process. See 14.4",
"D. Incorrect. Internal or external financial audits are independent corporate governance activities completely outside the scope of a project change authority. See 13.1"
]
},
{
exam: 2,
qnum: 18,
q: "Which report is generated periodically by a team manager to provide the project manager with regular updates on work package progress?",
opts: [
"Highlight report",
"Checkpoint report",
"End stage report",
"Exception report"
],
correct: 1,
explanation: [
"A. Incorrect. A highlight report is sent by the project manager to the project board, not by a team manager to the project manager. See 12.2.2",
"B. Correct. A checkpoint report is the standard operational progress update compiled by a team manager to report the status of a work package to the project manager. See 12.2.2",
"C. Incorrect. An end stage report is compiled by the PM at a stage boundary to summarize the performance of the entire completed stage for the board. See 12.2.2",
"D. Incorrect. An exception report is used specifically to escalate a tolerance breach, not for regular periodic progress reporting. See 12.4"
]
},
{
exam: 2,
qnum: 19,
q: "What process is triggered by the arrival of a project mandate from corporate management or programme commissioning?",
opts: [
"Initiating a project",
"Starting up a project",
"Directing a project",
"Managing a stage boundary"
],
correct: 1,
explanation: [
"A. Incorrect. Initiating a project is the first formal stage of the project and requires an approved project brief and authorization from the board, which comes after startup. See 14.2, 15.1",
"B. Correct. The project mandate is the external trigger document that initiates the pre-project process called 'starting up a project' (SU). See 14.1, 14.3",
"C. Incorrect. Directing a project runs continuously from the end of startup until project closure, providing governance decisions, but it is not the immediate process triggered by a raw mandate. See 13.1",
"D. Incorrect. Managing a stage boundary occurs at the end of an active management stage during the execution lifecycle, not at the very beginning of pre-project work. See 18.1"
]
},
{
exam: 2,
qnum: 20,
q: "What is an objective of the 'closing a project' process?",
opts: [
"To draft the initial project brief and appoint the executive",
"To ensure that provisions are made for project products to face regular post-project benefits reviews",
"To authorize the expenditure for the upcoming delivery stage",
"To select the specific configuration management software tools"
],
correct: 1,
explanation: [
"A. Incorrect. Appointing roles and drafting the brief happens in the pre-project 'starting up a project' process. See 14.1",
"B. Correct. An objective of closing a project is to ensure that the mechanisms for measuring realized benefits after the project has dismantled are fully integrated into the benefits management approach. See 19.2",
"C. Incorrect. Authorizing stage budgets is a direct responsibility of the project board within the 'directing a project' process, usually at a stage boundary. See 13.2",
"D. Incorrect. Choosing software infrastructure tools belongs in the initiation phase when establishing the management approaches. See 11.2.1, 12.2.3"
]
},
{
exam: 2,
qnum: 21,
q: "In which step of the business case management technique should the project mandate be reviewed?",
opts: [
"Develop",
"Check",
"Maintain",
"Confirm"
],
correct: 0,
explanation: [
"A. Correct. The 'Develop' step includes creating the outline business case from the project mandate during starting up a project, which begins with checking the mandate content. See 5.3",
"B. Incorrect. 'Check' is performed during stage gates or key reviews to ensure the business case remains valid, not the initial review of the mandate. See 5.3",
"C. Incorrect. 'Maintain' involves updating the business case with actual costs and revised forecasts throughout the stages. See 5.3",
"D. Incorrect. 'Confirm' is looking back post-project or at boundaries to verify if the actual benefits are achieved. See 5.3"
]
},
{
exam: 2,
qnum: 22,
q: "Which principle is being applied by the 'organizing' practice when the project executive ensures that decisions align to changing business needs?",
opts: [
"Focus on products",
"Ensure continued business justification",
"Learn from experience",
"Manage by exception"
],
correct: 1,
explanation: [
"A. Incorrect. Focus on products ensures clarity on specifications and deliverables, not overarching strategic and business alignment decision-making. See 2.5",
"B. Correct. The executive represents the business stake and must constantly guarantee that the project maps back to organizational priorities and a valid investment justification. See 2.1, 5.3",
"C. Incorrect. Learning from experience concerns capturing lessons learned from past mistakes and successes. See 2.2",
"D. Incorrect. Manage by exception governs the delegation of boundaries and tolerances between different tiers of control. See 2.4"
]
},
{
exam: 2,
qnum: 23,
q: "A new department head wants to know which members of staff will be involved in the project. Which management product should the department head review?",
opts: [
"Project management team structure",
"Role descriptions",
"Project log",
"Project board"
],
correct: 0,
explanation: [
"A. Correct. The project management team structure visually represents all roles, lines of authority, and specific human allocations for the project. See 4.3",
"B. Incorrect. Role descriptions provide details on the duties and accountabilities of generic roles, but don't show the full context of everyone involved at once. See 4.3",
"C. Incorrect. The project log is an operational document combining different items (lessons, daily tracking), not an organizational design view. See 12.2",
"D. Incorrect. The project board is just the top governance layer, not the entire structure showing all staff involvement. See 4.3"
]
},
{
exam: 2,
qnum: 24,
q: "Identify the missing word(s) in the following sentence: 'PRINCE2 uses the term [?] to cover all people required to allocate their time to the project.'",
opts: [
"Stakeholders",
"Users",
"Project team",
"Project support"
],
correct: 2,
explanation: [
"A. Incorrect. Stakeholders include any individual or group affected by or affecting the project, including those who don't allocate work hours directly. See 4.1",
"B. Incorrect. Users are a specific subset who will operate, maintain, or output-benefit from the project assets. See 4.1",
"C. Correct. The project team covers all the internal execution resources, managers, and support roles committing hours directly to deliver the project scope. See 4.1",
"D. Incorrect. Project support is a specific administrative sub-role, not the umbrella term for all project human resources. See 4.3"
]
},
{
exam: 2,
qnum: 25,
q: "According to the guidance for effective organizing, how should the commissioning party contribute to a project when it is started?",
opts: [
"By identifying the project executive in the project mandate",
"By setting sustainability targets on a stage-by-stage basis",
"By authorizing any breach of a project level tolerance that arises",
"By being responsible for the overall management of the project"
],
correct: 0,
explanation: [
"A. Correct. The corporate, program, or customer commissioning level initiates the project with a mandate, which must specify who the appointed project executive is. See 4.3, 14.3",
"B. Incorrect. Stage-by-stage targets and tracking are handled within the project board and project manager structures, not corporate commissioning directly. See 12.1",
"C. Incorrect. Project level tolerance exceptions are escalated to corporate/program management, but it's a reaction to an exception, not a starting contribution. See 12.4",
"D. Incorrect. The project manager is responsible for the active overall management of the project day-to-day. See 4.3"
]
},
{
exam: 2,
qnum: 26,
q: "In which step of the organizational design and development technique should responsibility for setting personal objectives be agreed?",
opts: [
"Understand the organizational ecosystem",
"Develop the project ecosystem",
"Design the project ecosystem",
"Transition the project into the organizational ecosystem"
],
correct: 1,
explanation: [
"A. Incorrect. Understanding the ecosystem gathers data about existing roles, capabilities, and cultural setups. See 4.4",
"B. Correct. During the 'Develop' step, specific operating protocols, team boundaries, personal performance rules, and growth targets are detailed and committed. See 4.4",
"C. Incorrect. Designing focuses on modeling structures, layers, and matching roles to requirements conceptually. See 4.4",
"D. Incorrect. Transitioning occurs during closure, offboarding human assets and releasing them back to line functions. See 4.4"
]
},
{
exam: 2,
qnum: 27,
q: "How should approved plans enable control?",
opts: [
"Plans should provide the baseline from which the schedule can be developed",
"Plans should be used to monitor progress and assess the impact of issues and risks",
"Plans should be updated as soon as a change in the project scope is identified to show the revised scope",
"Plans for the project as a whole include estimates that are the most accurate"
],
correct: 1,
explanation: [
"A. Incorrect. The schedule is a subset/component of the plan itself, not something created completely separately afterwards. See 6.1",
"B. Correct. Approved baselined plans form the fundamental yardstick. The project manager checks regular performance against them to monitor variances, risks, and modifications. See 6.1",
"C. Incorrect. A baseline plan shouldn't be altered immediately without passing a formal change request and getting approval from the correct governance layer. See 11.3",
"D. Incorrect. High-level project plans are often less accurate than near-horizon stage plans due to the planning horizon constraint. See 6.1"
]
},
{
exam: 2,
qnum: 28,
q: "The team manager needs to check what products should be delivered by his team. Which management product should the team manager review?",
opts: [
"Project product description",
"Work package description",
"Stage plan",
"Project plan"
],
correct: 1,
explanation: [
"A. Incorrect. The project product description is a high-level product defining the ultimate final asset for the customer. See 6.2",
"B. Correct. A work package description functions as the operational boundary assignment given to a team manager, containing explicit details on exactly what products must be produced. See 6.2, 16.2",
"C. Incorrect. The stage plan belongs to the project manager to track the complete stage; it encompasses multiple work packages across different teams. See 6.2",
"D. Incorrect. The project plan outlines the high-level roadmap and timeline for the entire project lifecycle. See 6.2"
]
},
{
exam: 2,
qnum: 29,
q: "What is defined as a high-level plan showing the major products of the project?",
opts: [
"A project plan",
"A stage plan",
"A team plan",
"A work package"
],
correct: 0,
explanation: [
"A. Correct. The project plan provides the strategic view of the whole project, highlighting main deliverables, key milestones, and critical control points. See 6.2",
"B. Incorrect. A stage plan is a detailed tactical breakdown focused exclusively on a single management stage. See 6.2",
"C. Incorrect. A team plan is optional, created by a team manager to coordinate specific day-to-day internal resources. See 6.2",
"D. Incorrect. A work package is a formal allocation mechanism, not an overarching plan document type. See 6.2"
]
},
{
exam: 2,
qnum: 30,
q: "How should the project manager address the planning horizon?",
opts: [
"By preparing a complete and detailed project plan based on accurate estimates",
"By preparing a stage plan for the next stage based on more accurate estimates",
"By identifying the major products and activities in the project plan",
"By identifying interdependencies between major products in the stage plan"
],
correct: 1,
explanation: [
"A. Incorrect. It is impossible to plan everything in exhaustive detail upfront due to the planning horizon limitation. See 6.1.2",
"B. Correct. PRINCE2 counters the planning horizon issue by keeping the project plan high-level and only creating detailed stage plans close to the actual execution of that stage. See 6.1.2",
"C. Incorrect. While this is done, it describes project plan construction rather than the strategy used to tackle the horizon problem directly. See 6.1.2",
"D. Incorrect. Interdependencies are mapped out as a standard step in planning, but it doesn't solve the long-term forecast visibility challenge. See 6.1.2"
]
},
{
exam: 2,
qnum: 31,
q: "In which step of the planning technique should the project manager identify the equipment needed to deliver the plan?",
opts: [
"Preparing estimates",
"Defining and analysing the products",
"Organizing work packages",
"Preparing a schedule"
],
correct: 0,
explanation: [
"A. Correct. The 'Preparing estimates' step calculates the necessary effort, resource types, equipment, tools, and materials required to fulfill the defined tasks. See 6.3",
"B. Incorrect. Defining and analyzing products creates the product breakdown structures and product descriptions. See 6.3",
"C. Incorrect. Organizing work packages is an operational step about grouping and assigning elements, not resource-need estimation. See 6.3",
"D. Incorrect. Preparing a schedule sets the chronological sequence, critical paths, and calendar dates for execution. See 6.3"
]
},
{
exam: 2,
qnum: 32,
q: "What is a description of a purpose of the quality practice?",
opts: [
"To define how the project's products will be tested to obtain their acceptance",
"To define how the project executive will decide whether the benefits exceed the costs",
"To enable the project team to communicate effectively by defining how the products will be delivered",
"To collect and assess off-specifications and control changes to the agreed project scope"
],
correct: 0,
explanation: [
"A. Correct. The purpose of the quality practice is to operationalize quality criteria and state the methods for inspection, testing, and verifying that deliverables match expectations. See 8.1",
"B. Incorrect. Cost-benefit viability decisions belong directly to the business case practice. See 5.1",
"C. Incorrect. Delivery mechanisms and communication protocols relate to the organizing and planning practices. See 4.1, 6.1",
"D. Incorrect. Controlling modifications and handling off-specifications belongs to the issues practice. See 11.1"
]
},
{
exam: 2,
qnum: 33,
q: "The project manager needs to check when an output is planned to be inspected. Which management product should the project manager review?",
opts: [
"Quality management approach",
"Product description",
"Product register",
"Quality register"
],
correct: 3,
explanation: [
"A. Incorrect. The quality management approach defines the generic strategies, rules, and corporate quality frameworks applied across the project. See 8.2",
"B. Incorrect. A product description details the quality criteria for that item, but doesn't track calendar dates for upcoming active test instances. See 8.2",
"C. Incorrect. There is no standard management product called the 'product register' in baseline PRINCE2 (configuration items can be in an issue/configuration context). See 11.2",
"D. Correct. The quality register acts as the calendar log containing target and actual testing dates, assigned inspectors, and pass/fail results. See 8.2"
]
},
{
exam: 2,
qnum: 34,
q: "Which describes quality specifications?",
opts: [
"They are applied when inspecting a finished product",
"They are applied when accepting the project product",
"They are documented in the project product description",
"They are documented in the quality management approach"
],
correct: 0,
explanation: [
"A. Correct. Quality specifications are the detailed technical thresholds or characteristics used during quality control to test whether a finished product conforms to its criteria. See 8.1.1",
"B. Incorrect. Ultimate project-level conditions are customer acceptance criteria, which differ slightly from micro-level product specifications. See 8.1.1",
"C. Incorrect. High-level project conditions live in the project product description, while individual component specifications live in separate product descriptions. See 8.1.1",
"D. Incorrect. The quality management approach governs the rules and processes, not individual asset specifications. See 8.2"
]
},
{
exam: 2,
qnum: 35,
q: "A building is being constructed as part of the project. The building needs to meet environmental targets. Which information should be recorded as part of quality planning?",
opts: [
"The quality activities to test the product's sustainability in the quality register",
"The test results after testing the product's environmental requirements",
"The environmental requirements as the specifications in the product description",
"The post project reviews to measure the sustainability targets in the benefits management approach"
],
correct: 2,
explanation: [
"A. Incorrect. Recording active test instances occurs during quality control execution, not during the upfront quality planning step. See 8.1.1",
"B. Incorrect. Test logs and actual result entries are part of quality control metrics gathered after work finishes. See 8.1.1",
"C. Correct. Quality planning requires establishing the criteria upfront; therefore, the environmental constraints must be explicitly stated inside that item's product description. See 8.1.1",
"D. Incorrect. Tracking long-term realization occurs post-project, whereas technical quality definition is an active, current project planning task. See 5.2, 8.1.1"
]
},
{
exam: 2,
qnum: 36,
q: "The project manager has prioritized the criteria that the project product must meet before the user will accept it. In which step of the quality management technique should this prioritization be used to define quality specifications?",
opts: [
"Gathering user inputs",
"Accepting products",
"Describing the quality management approach",
"Controlling quality"
],
correct: 0,
explanation: [
"A. Correct. The 'Gathering user inputs' step captures initial customer expectations, prioritizing them to define the core acceptance criteria and specifications for the final deliverable. See 8.3",
"B. Incorrect. Accepting products is the final verification step when handover signatures are gathered, long after definitions are made. See 8.3",
"C. Incorrect. Formulating the approach details generic procedures and tool frameworks, not individual asset attribute requirements. See 8.2",
"D. Incorrect. Controlling quality is the execution phase where actual outputs are measured against the baseline specifications. See 8.3"
]
},
{
exam: 2,
qnum: 37,
q: "Why should the risk practice be performed?",
opts: [
"To enable the project board to decide whether the outcomes and resulting benefits are likely to be achieved",
"To enable the project manager to predict whether the project will be delivered on time and cost",
"To identify the modifications to the current approved versions of the project products",
"To identify and manage opportunities that would positively affect achievement of the project objectives"
],
correct: 3,
explanation: [
"A. Incorrect. While it informs the board, this describes business case justification tracking rather than the comprehensive scope of risk management. See 10.1",
"B. Incorrect. Estimating parameters and timelines is an active focus of the plans and progress practices. See 6.1, 12.1",
"C. Incorrect. Managing configuration items and scope modifications belongs entirely to the issues practice. See 11.1",
"D. Correct. The purpose of the risk practice is to identify, assess, and control uncertainty—which fundamentally covers both threats (negative impacts) and opportunities (positive impacts). See 10.1"
]
},
{
exam: 2,
qnum: 38,
q: "The PRINCE2 procedure needs to be tailored to ensure events that are likely to affect the objectives are managed. In which management product should this be documented?",
opts: [
"Risk management approach",
"Risk register",
"Issue management approach",
"Issue register"
],
correct: 0,
explanation: [
"A. Correct. The risk management approach is the document that details exactly how the risk procedure will be customized, structured, and implemented for that specific project. See 10.2",
"B. Incorrect. The risk register is an ongoing repository for logging individual risks, not the strategy document for process tailoring. See 10.2",
"C. Incorrect. The issue management approach handles change requests, problems, and defects, not uncertainty risk procedures. See 11.2",
"D. Incorrect. The issue register logs active issues, not the overarching risk management framework rules. See 11.2"
]
},
{
exam: 2,
qnum: 39,
q: "Which term is defined as an uncertain event or set of events that, should it occur, will have an effect on the achievement of objectives?",
opts: [
"Risk",
"Off-specification",
"Request for change",
"Problem/concern"
],
correct: 0,
explanation: [
"A. Correct. This is the official PRINCE2 definition of a risk: an event characterized by its uncertainty, which can impact the project either negatively or positively. See 10.1",
"B. Incorrect. An off-specification is an active, factual deficiency or defect that has already occurred, not an uncertainty. See 11.1",
"C. Incorrect. A request for change is a deliberate proposal to alter a project baseline, not an unplanned hazard. See 11.1",
"D. Incorrect. Problems/concerns represent active issues that require manager intervention immediately. See 11.1"
]
},
{
exam: 2,
qnum: 40,
q: "How does effective risk management enable understanding of the overall risk exposure for a project?",
opts: [
"By positioning risks, in relation to the risk tolerance line, on a summary risk profile",
"By identifying different types of sustainability risks",
"By identifying, assessing and planning responses for each risk",
"By establishing a risk budget to fund management responses to risks"
],
correct: 0,
explanation: [
"A. Correct. A summary risk profile plots the probability and impact of multiple risks visually, showing where they sit against the risk tolerance boundary to show cumulative exposure. See 10.1",
"B. Incorrect. Evaluating sustainability factors is helpful, but isolating one risk type does not calculate the complete project-wide exposure. See 10.1",
"C. Incorrect. This describes the individual steps of the risk procedure rather than how a manager synthesizes them to assess aggregate project-wide exposure. See 10.1, 10.3",
"D. Incorrect. A risk budget is a pool of money allocated to pay for specific fallback strategies, not a tool used to understand exposure levels. See 10.1"
]
},
{
exam: 2,
qnum: 41,
q: "The project manager needs to review the project brief to decide who will be responsible for each step in the risk management technique. In which step of the risk management technique should this occur?",
opts: [
"Identify - define context and objectives",
"Identify - identify threats and opportunities",
"Assess - prioritize risks",
"Plan"
],
correct: 0,
explanation: [
"A. Correct. The 'Identify - define context and objectives' step establishes the baseline rules, project environment parameters, and clarifies ownership roles for the risk technique. See 10.3",
"B. Incorrect. Identifying threats/opportunities focuses on brainstorming and drafting explicit risk entries, not setting up technique ownership. See 10.3",
"C. Incorrect. Assessing risk handles prioritizing probability, impact, and closeness matrices. See 10.3",
"D. Incorrect. Planning involves formulation of specific tactical counter-options (like mitigate, avoid, or share). See 10.3"
]
},
{
exam: 2,
qnum: 42,
q: "The senior user is concerned that the scope of the project needs to be changed. When should the senior user raise this issue?",
opts: [
"As soon as the issue has been identified",
"At the next scheduled formal project meeting",
"At the next scheduled meeting of project board members",
"As the stage end approaches"
],
correct: 0,
explanation: [
"A. Correct. PRINCE2 dictates that issues should be captured and logged dynamically as soon as they are spotted to prevent delay or negative progression impacts. See 11.1, 11.3",
"B. Incorrect. Waiting for an administrative meeting creates artificial delay and can cause significant progress exceptions. See 11.3",
"C. Incorrect. Delaying until a project board meeting stalls vital adjustments that might need immediate investigation. See 11.3",
"D. Incorrect. Forcing change requests to wait until a stage boundary violates efficient progress tracking and agile adaptation. See 11.3"
]
},
{
exam: 2,
qnum: 43,
q: "The project manager wants to review the status of all events that are being considered by the project management team. Which management product should the project manager review?",
opts: [
"Issue register",
"Issue report",
"Risk register",
"Product register"
],
correct: 0,
explanation: [
"A. Correct. The issue register is the central operational list where all requests for change, off-specifications, and problems are tracked and monitored. See 11.2",
"B. Incorrect. An issue report is a separate narrative document used to detail a single, specific issue being escalated, not a multi-item register summary. See 11.2",
"C. Incorrect. The risk register tracks future uncertainties, not active occurring events/issues currently under management consideration. See 10.2",
"D. Incorrect. 'Product register' is not an official baseline tracking component for active project problem management. See 11.2"
]
},
{
exam: 2,
qnum: 44,
q: "What is the definition of a request for change?",
opts: [
"A proposal for a change to a baseline",
"Something that should be provided but has not been provided",
"An uncertain event which may affect objectives",
"The current versions of project products that are subject to change control"
],
correct: 0,
explanation: [
"A. Correct. A request for change ($RFC$) is a formal proposal to modify an approved project baseline (such as scope, budget, or timelines). See 11.1",
"B. Incorrect. A missing requirement or structural defect describes an off-specification. See 11.1",
"C. Incorrect. An uncertain event represents a project risk, not an active issue or proposal. See 10.1, 11.1",
"D. Incorrect. Current baseline states represent configuration items or asset versions, not the proposal itself. See 11.1"
]
},
{
exam: 2,
qnum: 45,
q: "The project board has delegated significant change authority to several roles in the project management team. What negative effect could directly result from this?",
opts: [
"Most changes to product descriptions may be generated by team members",
"The actual and authorized status of products recorded in the product register may not agree",
"The project board may be slow to make decisions, delaying delivery progress",
"The project scope may become less aligned to the business case"
],
correct: 3,
explanation: [
"A. Incorrect. Team members drafting descriptions is a natural execution task, not a critical corporate risk of delegating change permissions. See 11.1",
"B. Incorrect. Status inconsistencies stem from weak configuration tracking, not from who owns the approval authority. See 11.1",
"C. Incorrect. Delegating authority actually speeds up operational decision-making, rather than slowing the board down. See 11.1",
"D. Correct. If too much independent change authority is spread out without strong oversight, cumulative micro-changes can alter the project scope and drift away from the core business justification. See 11.1"
]
},
{
exam: 2,
qnum: 46,
q: "The project manager needs to consider the impact of an issue on the benefits and costs. In which step of the issue management technique should this occur?",
opts: [
"Assessing issues",
"Capturing issues",
"Deciding on changes",
"Implementing changes"
],
correct: 0,
explanation: [
"A. Correct. The 'Assessing issues' step explicitly evaluates how an issue influences the overall project parameters, including costs, schedules, quality, and business case benefits. See 11.3",
"B. Incorrect. Capturing issues is simply logging and categorizing the incoming concern or proposal. See 11.3",
"C. Incorrect. Deciding on changes happens after the impact analysis is done, when a formal choice is chosen. See 11.3",
"D. Incorrect. Implementing changes executes the approved response and updates affected products. See 11.3"
]
},
{
exam: 2,
qnum: 47,
q: "Which statement BEST describes where progress should be monitored?",
opts: [
"At stage boundaries at the end of each stage",
"At the project, stage, and work package level",
"At the product delivery level",
"At project closure when project costs are being calculated"
],
correct: 1,
explanation: [
"A. Incorrect. Monitoring only at stage ends is insufficient for day-to-day control and risk minimization. See 12.1",
"B. Correct. Progress tracking must occur across all distinct control tiers of the project organization: project-level (board), stage-level (PM), and work package-level (team managers). See 12.1",
"C. Incorrect. Just focusing on team delivery ignores the broader stage budgets and overall strategic project tolerances. See 12.1",
"D. Incorrect. Post-project calculation is a retroactive evaluation, not an active progress control mechanism. See 12.1"
]
},
{
exam: 2,
qnum: 48,
q: "The project manager needs to inform the project board of what approved products are outstanding before the project board approves further work. In which management product should the project manager record this information?",
opts: [
"Checkpoint report",
"Highlight report",
"End stage report",
"End project report"
],
correct: 2,
explanation: [
"A. Incorrect. Checkpoint reports are compiled by team managers for the PM, not for the project board. See 12.2",
"B. Incorrect. Highlight reports are periodic mid-stage status summaries, not the comprehensive review required before approving a major new stage. See 12.2",
"C. Correct. An end stage report is prepared by the PM at the end of a stage to give the board an overview of what was achieved and what is outstanding, helping them decide whether to authorize the next stage. See 12.2, 18.2",
"D. Incorrect. The end project report is created at closure to wrap up the entire project, not to request approval for ongoing stages. See 12.2"
]
},
{
exam: 2,
qnum: 49,
q: "Identify the missing word in the following sentence: 'The business layer, outside the project team, sets the overall requirements and [?] levels for the project.'",
opts: [
"Tolerance",
"Issue",
"Forecast",
"Risk"
],
correct: 0,
explanation: [
"A. Correct. The external corporate or program commissioning layer sets the overarching project-level tolerances (such as maximum budget or final date boundaries). See 12.1",
"B. Incorrect. 'Issue levels' is not a standard term used to define external commissioning boundaries. See 12.1",
"C. Incorrect. Forecasts are calculated by the project manager based on active work velocity, not fixed by the business layer. See 12.1",
"D. Incorrect. While the corporate layer sets the overall risk appetite, the specific operational boundaries for project variance are called tolerances. See 12.1"
]
},
{
exam: 2,
qnum: 50,
q: "The project mandate set a firm date for the delivery of the project. It has now been agreed that the project can be delayed by up to 4 weeks. Which level of management should agree this?",
opts: [
"Project board",
"Project manager",
"Business layer",
"Team manager"
],
correct: 2,
explanation: [
"A. Incorrect. The project board only owns tolerances at the project level. Changing a firm baseline set in the external mandate requires corporate escalation. See 12.1, 12.4",
"B. Incorrect. The project manager only manages within the tolerances allocated for the current stage. See 12.1",
"C. Correct. Altering the final project delivery dates specified in the mandate changes a project-level constraint, meaning it must be approved by the external business layer (corporate or program management). See 12.1, 12.4",
"D. Incorrect. Team managers operate within work package boundaries and cannot change project schedules. See 12.1"
]
},
{
exam: 2,
qnum: 51,
q: "What action may be taken by a project manager when an issue causes one of the stage tolerances to be exceeded?",
opts: [
"Accept or reject the recommendation from the exception report",
"Resolve the issue within other project tolerances and include in the next highlight report",
"Escalate to the business layer for advice and direction to implement the exception report",
"Resolve the issue using other stage tolerances and include in the next highlight report"
],
correct: 1,
explanation: [
"A. Incorrect. The project manager writes the exception report; it is the project board that accepts or rejects its recommendations. See 12.4",
"B. Correct. If a stage tolerance is breached, it creates an exception. However, if the issue can be absorbed within broader project-level boundaries, the PM escalates it via an exception report to the board, who can adjust tolerances and log it in progress updates. See 12.4",
"C. Incorrect. The project manager escalates to their immediate superior body (the project board), not directly past them to the corporate business layer. See 12.4",
"D. Incorrect. If a stage tolerance is exceeded, the PM has no authority to fix it locally with other stage parameters without formal board intervention. See 12.4"
]
},
{
exam: 2,
qnum: 52,
q: "Which is a description of a purpose of the 'initiating a project' process?",
opts: [
"To define how long it will take for the project to deliver what is required to gain acceptance",
"To enable control between the project manager and team managers",
"To review, at a high level, whether the project will add value to an organization",
"To assess whether a project has been delivered on time and that it has nothing more to contribute"
],
correct: 0,
explanation: [
"A. Correct. The purpose of initiating a project ($IP$) is to establish solid foundations by mapping out timelines, costs, risk approaches, and quality parameters so the organization understands the commitment before spending significant budget. See 15.1",
"B. Incorrect. Controlling work package delivery between the PM and team managers is handled by the 'controlling a stage' and 'managing product delivery' processes. See 16.1, 17.1",
"C. Incorrect. High-level viability checks are done earlier during the pre-project 'starting up a project' process. See 14.1",
"D. Incorrect. Assessing final performance and evaluating the close of work belongs to the 'closing a project' process. See 19.1"
]
},
{
exam: 2,
qnum: 53,
q: "The team manager needs to agree what products need to be produced, and when. In which process should this be agreed?",
opts: [
"Managing product delivery",
"Directing a project",
"Managing a stage boundary",
"Controlling a stage"
],
correct: 0,
explanation: [
"A. Correct. The purpose of 'managing product delivery' ($MPD$) is to structure the relationship between the PM and the team manager, ensuring that work packages are formally accepted, executed, and delivered to specification. See 17.1",
"B. Incorrect. Directing a project handles senior executive governance and high-level authorizations, not team-level task agreements. See 13.1",
"C. Incorrect. Managing a stage boundary looks ahead to plan the next stage framework at a macro level, not individual team assignments. See 18.1",
"D. Incorrect. While controlling a stage is where the PM coordinates work, the actual agreement, creation, and handover of specialist products by a team happens within 'managing product delivery'. See 16.1, 17.1"
]
},
{
exam: 2,
qnum: 54,
q: "In which process is the work undertaken to assess whether all the objectives given in the current project initiation documentation have been achieved?",
opts: [
"Closing a project",
"Controlling a stage",
"Managing product delivery",
"Managing a stage boundary"
],
correct: 0,
explanation: [
"A. Correct. The 'closing a project' ($CP$) process is where the PM conducts a final review against the project initiation documentation ($PID$) to verify that all intended outputs have been delivered and accepted. See 19.1",
"B. Incorrect. Controlling a stage tracks performance during an active execution interval, not the final project shutdown. See 16.1",
"C. Incorrect. Managing product delivery checks component quality at the team level, not overall project-level objectives. See 17.1",
"D. Incorrect. Managing a stage boundary checks stage-specific results to transition to the next stage, not final project closure. See 18.1"
]
},
{
exam: 2,
qnum: 55,
q: "Which TWO are objectives of the 'starting up a project' process?\n1. To define the scope of the project to enable it to be initiated\n2. To authorize the work to deliver the project product\n3. To understand what quality techniques will be applied in the project\n4. To assess the alternative ways of delivering the project",
opts: [
"1 and 2",
"2 and 3",
"3 and 4",
"1 and 4"
],
correct: 3,
explanation: [
"1. Correct. Establishing sufficient scope clarity to support initiation is a core objective of startup. See 14.2",
"2. Incorrect. Authorizing specialist delivery work happens during the execution stages, not during pre-project startup. See 13.2, 16.1",
"3. Incorrect. Designing the specific quality techniques and approaches is a key focus of the initiation stage ('initiating a project' process). See 15.2",
"4. Correct. Evaluating alternative delivery strategies (e.g., buying vs. building) is an objective of startup to shape the project brief. See 14.2",
"Therefore, Option D (1 and 4) is correct."
]
},
{
exam: 2,
qnum: 56,
q: "Which TWO activities support the objectives of the 'directing a project' process?\n1. Authorize that the project team should be disbanded as work is complete\n2. Review plans to measure the benefits after the project has closed\n3. Check that the products can be supported by operations after the project is closed\n4. Verify that the users requirements have been met",
opts: [
"1 and 2",
"2 and 3",
"3 and 4",
"1 and 4"
],
correct: 0,
explanation: [
"1. Correct. The project board is responsible for authorizing project closure and disbanding the management team once work is confirmed complete. See 13.2",
"2. Correct. The board reviews and maintains oversight of the post-project benefits management approach to ensure measurements will take place. See 13.2",
"3. Incorrect. Checking operational support readiness is an operational task handled by the PM and support staff during project closure. See 19.3",
"4. Incorrect. Detailed verification of user technical requirements is a quality control activity managed by the PM, users, and team managers. See 8.3, 17.3",
"Therefore, Option A (1 and 2) is correct."
]
},
{
exam: 2,
qnum: 57,
q: "Which TWO are objectives of the 'controlling a stage' process?\n1. To respond to risks and issues as they are raised\n2. To plan the detailed activities for the next stage of the project\n3. To define the controls for the project\n4. To continually assess the business justification",
opts: [
"1 and 2",
"2 and 3",
"3 and 4",
"1 and 4"
],
correct: 3,
explanation: [
"1. Correct. Managing daily changes, logging issues, and implementing risk responses is a core objective of controlling a stage. See 16.2",
"2. Incorrect. Detailed planning for the upcoming stage occurs in the 'managing a stage boundary' process. See 18.2",
"3. Incorrect. Defining project-wide management controls is a foundational task completed during the initiation stage. See 15.2",
"4. Correct. The PM must continually ensure that stage execution remains aligned with a valid business justification. See 16.2",
"Therefore, Option D (1 and 4) is correct."
]
},
{
exam: 2,
qnum: 58,
q: "During the 'managing a stage boundary' process, when should the project manager replan the rest of the stage?",
opts: [
"After reporting to the project board that a stage tolerance is likely to be exceeded",
"After receiving advice from the project board in response to a highlight report during the stage",
"After requesting the project board to approve an exception plan for the stage",
"After requesting the project board to approve a change to the project team delivering the stages products"
],
correct: 2,
explanation: [
"A. Incorrect. Reporting a forecast breach is the initial step (escalation), but you don't build the formal exception plan baseline until authorized or directed. See 12.4, 18.2",
"B. Incorrect. Highlight reports are used for standard status updates, not for triggering a complete mid-stage re-plan. See 12.2",
"C. Correct. If a stage tolerance is breached, the board will typically request an exception plan. The PM creates this plan during the 'managing a stage boundary' process to replace the remainder of the current stage plan. See 18.2",
"D. Incorrect. Adjusting team resourcing is an operational change that does not require a formal exception re-plan of the entire stage boundary. See 16.2"
]
},
{
exam: 2,
qnum: 59,
q: "Which describes how the 'controlling a stage' process may be used?",
opts: [
"It could be used by the project manager to monitor the initiation stage of a large project",
"It could be omitted if the team manager role is being fulfilled by the project manager",
"It could be merged with the 'managing a stage boundary' process if appropriate",
"It could be omitted if the team managers are internal to the business"
],
correct: 0,
explanation: [
"A. Correct. The initiation stage is a formal management stage in PRINCE2. For large or complex projects, the PM uses 'controlling a stage' ($CS$) to monitor and manage initiation activities just like any delivery stage. See 16.1",
"B. Incorrect. Even if the PM acts as their own team manager, the management controls and tracking of 'controlling a stage' are still mandatory. See 16.1",
"C. Incorrect. Controlling a stage (execution) and managing a stage boundary (planning ahead/reviewing) serve distinct governance purposes and cannot be merged. See 16.1, 18.1",
"D. Incorrect. Internal or external resourcing does not change the requirement for formal stage management and control. See 16.1"
]
},
{
exam: 2,
qnum: 60,
q: "Which describes a project characteristic that drives the need for the 'closing a project' process?",
opts: [
"A project should hand over the desired change to business as usual",
"A project is delivered using a new project team",
"A project uses resources from different departments",
"A project deals with higher levels of uncertainty"
],
correct: 0,
explanation: [
"A. Correct. Projects are temporary structures designed to introduce change. Because they have a defined end point, a formal closing process ($CP$) is required to hand over products cleanly to operations (business as usual) and dismantle the project structure. See 1.3, 19.1",
"B. Incorrect. While project teams can be new, it is the temporary nature of the endeavor—not the team's familiarity—that necessitates formal closure. See 1.3",
"C. Incorrect. Cross-functional resourcing is a common characteristic, but the requirement to close work stems from its temporary lifecycle. See 1.3",
"D. Incorrect. Uncertainty drives the need for effective risk and progress practices, whereas closure is driven by the project being temporary. See 1.3, 19.1"
]
}
];